Year 2017- 2018 Dec Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec Complete Tech Memos Prepare Design Report Prepare Procurement Documents -SBR -Grit Removal, UV Equipment Bid Equipment Bid Award Vendor Shop Drawings Grant Applications -Public Hearing -DNRC RRGL May 15th -TSEP May 4th Final Design Year 2019 Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec Final Design Project Bidding Construction Start Year 2020 Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec Construction Year 2021 Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec Construction Completion AOC Date Plant Startup and Compliance AOC Date Estimated Completion Date CITY OF WHITEFISH Wastewater Treatment Plant Improvements - Project Schedule Submission & Review