Knife River East 2nd Street Reconstrution Item Duration Start Finish 9 10 11 12 13 16 17 18 19 20 23 24 25 26 27 30 1 2 3 7 8 9 10 11 14 15 16 17 18 21 22 23 24 25 28 29 30 31 1 4 5 6 7 8 11 12 13 14 15 18 19 20 21 22 25 26 27 28 29 1 2 3 4 5 8 9 10 11 12 15 16 17 18 19 22 23 24 25 Rotomilling 3 6/9 6/11 Muck Excavation 4 6/9 6/20 Rock Embankment 5 6/9 6/26 Uncrushed Sub-Base 4 6/26 7/1 Wetland Mitigation 3 6/9 6/30 Sanitary Sewer West 7 6/11 6/19 Sanitary Sewer East 14 6/18 7/8 Temp Water 3 7/1 7/3 Water 15 7/7 7/25 Storm Drain East 10 7/21 8/1 Cow Creek Sanitary Sewer 5 8/4 8/8 Cow Creek Box Culvert 6 8/8 8/15 Storm Drain West 4 8/14 8/20 Site Prep/Grading 25 7/7 8/22 Fabric 8 7/31 8/25 Crushed Base Course 14 7/31 8/26 Asphalt Paving 5 9/1 9/5 Curb & Gutter 10 8/18 8/29 Median Curb 1 9/8 9/8 Median Cap 1 9/9 9/9 Sidewalk 32 7/28 9/9 Signs 4 9/10 9/15 Striping 1 9/10 9/10 Landscaping 15 9/8 9/25 Area 1 Closure 14 8/7 8/20 Area 3 Closure 21 7/14 8/1 June July August September