← Back to Whitefish

Document Whitefish_doc_6c21e45323

Full Text

City of Whitefish Department of Public Works 418 E. 2nd Street I PO Box 158 Whitefish, MT 59937 (406) 863-2460 I Fax (406) 863-2419 December 10, 2019 Mayor Muhlfeld and City Councilors City of Whitefish Whitefish, Montana Mayor Muhlfeld and Councilors Award of Wastewater Treatment Plant Construction Contract to Swank Enterprises Introduction/History The City was issued an Administrative Order of Consent (AOC) by the Montana Department of Environmental Quality (DEQ) on October 5, 2012. The AOC currently includes a Compliance Plan detailing the completion dates that must be met in order to bring the WWTP into compliance with updated requirements for removal of ammonia, nitrogen and phosphorous in the city’s updated wastewater discharge permit. As part of the AOC, the Whitefish City Council approved a Preliminary Engineering Report (PER) in 2016 recommending that a mechanical wastewater treatment facility be designed and constructed in the location of the city’s existing wastewater lagoons. Current Report The type of wastewater treatment plant selected for construction in the Whitefish wastewater system planning process is called a Sequencing Batch Reactor, or SBR. An SBR is a type of activated sludge plant where multiple unit processes are contained within the same concrete basin, saving space and cost. Generally, when selecting a SBR system, an engineer will bid the equipment initially and design the treatment plant around a specific type of equipment, allowing for a better and more cost-effective design. The equipment was bid in September 2018 and we received seven different bids from five vendors. Upon consideration of all the pertinent factors, the scoring of proposals was extremely close for two types of treatment processes - the Sanitaire SBR process and the Aqua-Aerobic AquaNereda (Nereda®) system. While the Nereda® equipment bid was greater than the others, the system requires much smaller basins, and a significant reduction in overall footprint. ---PAGE BREAK--- Re: Award of Wastewater Treatment Plant Construction December 10, 2019 Page I 2 of 3 Consequently, after factoring in concrete and foundation expense, the Nereda® system ultimately was the least expensive overall option. Additionally, the operating costs for the Nereda® system were projected to be much less than the Sanitaire system due to lower energy requirements. In more practical terms, this technology will allow us to build smaller basins which are less than ⅓ the size of more traditional SBR basins, allowing for construction savings, reduced energy consumption, and more effective use of the land at the treatment plant site. The much smaller footprint allowed moving the treatment plant outside of the existing treatment lagoon cells, resulting in further cost savings. The City ultimately decided on the Nereda® system and the equipment contract was awarded to Aqua-Aerobic on December 3, 2018. Once the equipment procurement process was complete, the City was able to proceed with the final design for the wastewater plant improvements. The goal was to complete the design and advertise the project for bids last summer, however, the complexity of the process and the fact that Whitefish is the first “greenfield” Nereda project in the U.S., required significant communication between our design engineers, and Aqua-Aerobics and developers of the proprietary technology – Royal in the Netherlands. Early in the design phase, it was determined that improvements were necessary for the effluent outfall and diffuser, sludge drying beds, and Administration Building so the overall project scope was adjusted to incorporate these needs. Ultimately, plans were completed in September and submitted to DEQ for approval. Final approval was received from DEQ on October 16, 2019. Financial Requirement Once the plans were approved by DEQ, the construction of the wastewater plant was advertised, and bids were opened on Tuesday November 19. A total of two bids were received ranging from $20,370,000 (Swank Enterprises) to $23,145,616 (Dick Anderson Construction). The engineer’s estimate was $16,683,973, meaning bids exceeded the estimate by 22% - 39%. The assessment of the bidding process indicates that several factors may have impacted the bid including limited number of bidders, other similarly-sized projects bidding at the same time, project complexity, use of proprietary technology, impact of the American Iron and Steel requirements, expensive dirt work and the involved control system. The low bidder, Swank Enterprises, spent a lot of time investigating the project and asking questions so we do believe that their bid is an accurate representation of the true cost of the project, in the current bidding climate. The Nereda® system was estimated to be $1.3 million less in capital costs when considering concrete and foundation cost differences. Upon receipt of the schedule of values from Swank, a calculation was performed to determine if the Nereda® system would provide this much savings. Net estimated capital cost savings resulting from choosing the Aqua technology over Sanitaire was estimated at $2.29M. Staff also worked with our engineers to determine whether there are elements of the project that could be eliminated or modified. While this “value engineering” exercise proved that the ---PAGE BREAK--- Re: Award of Wastewater Treatment Plant Construction December 10, 2019 Page I 3 of 3 system we design was extremely streamlined, we were able to identify approximately $475,000 in work that can be eliminated. Here is a brief description of those recommendations: 1. $334,461 - Omit all drying bed restoration The project included the restoration of the three biosolids drying beds at the plant. While this work needs to be completed, staff believes it can be done using city crews at a reduced cost. 2. $35,785 - Omit hauling and disposal of lagoon cell 3 sludge The contractor will move wet sludge to one of the existing drying beds for the city crew to remove at its convenience after significant dewatering has occurred. 3. $50,230 - Omit plant decommissioning Leave lagoon cells 1 and 2 as they are. Leave air piping to cell 2. Leave contents in flocculating clarifier. City would be responsible for pumping approximately 24MG of water to the drain to MLS or to the grit channel. 4. $54,733 - Provide continuous venting strips in lieu of specified vent/drain Liner system for biosolids basin would be modified to include fabric strips capable of minimizing gas accumulation beneath the liner. In total this exercise provided $475,209 in potential savings. An updated budget has been provided which incorporates these value engineering changes, final engineering fees, contingency, and tipping fees for landfill disposal of biosolids. Recommendation After continuous discussion between city staff, our engineers, Swank Enterprises, and Aqua Aerobic over the past month, the Public Works Department is confident that it is in the best interest of the city for Swank Enterprises to build the wastewater treatment plant. Swank is a reputable firm that has successfully completed countless projects throughout Montana. In addition, the plant that has been designed and bid is the most cost-effective solution to regain compliance with DEQ and will serve the city for decades to come. Based on these factors, it is the recommendation of the Public Works Department that Council award the Wastewater Treatment Plant Construction Project to Swank Enterprises in the amount of $20,370,000. As soon as the project is awarded, a change order will be executed reducing the contract price to approximately $19,895,000 based on final value engineering negotiations. Sincerely, Craig Workman, P.E. Director of Public Works ---PAGE BREAK--- Item Unit Estimated Quantity Item Name Unit Price Total Price Unit Price Total Price Unit Price Total Price No. 100 LS 1 Mobilization/Insurance/Bonding $1,516,725.00 $1,516,725.00 $1,750,000.00 $1,750,000.00 $1,000,000.00 $1,000,000.00 110 LS 1 Improvements to the $12,919,632.00 $12,919,632.00 $19,148,000.00 $19,148,000.00 $17,122,384.00 $17,122,384.00 120 LS 1 Price for Contractor's Payment Obligations to Aqua Aerobics $2,247,616.00 $2,247,616.00 $2,247,616.00 $2,247,616.00 $2,247,616.00 $2,247,616.00 Eng. Estimate Dick Anderson Swank $16,683,973 $23,145,616.00 $20,370,000.00 Swank Enterprises Base Bid: These Bid Tabulations are an accurate representation of the bids received on November 19, 2019 by the City of Whitefish for the Project 2019. Whitefish Wastewater Treatment Plant Improvements Project 2019 Certified Bid Tabulations - November 19, 2019 Bid Items Engineer's Estimate Dick Anderson Construction ---PAGE BREAK--- 4 - PROJECT BUDGET FORM December-19 ADMIN/FINANCIAL COSTS RRGL Grant TSEP Grant SRF Loan SRF Forgiven Principal** Local Reserves TOTAL Personnel Costs $0 $0 $0 $0 $0 $0 Professional Services $0 $0 $75,000 $0 $0 $75,000 Legal Costs $0 $0 $70,000 $0 $0 $70,000 Travel & Training $0 $0 $7,500 $0 $0 $7,500 Loan Reserves (½ annual P&I) $0 $0 $649,000 $0 $0 $649,000 Interim Interest $0 $0 $0 $0 $0 $0 Bond Cost $0 $0 $75,000 $0 $0 $75,000 TOTAL ADMIN/FIN. COSTS $0 $0 $876,500 $0 $0 $876,500 3.5% ACTIVITY COSTS: RRGL TSEP SRF SRF - FP Loan Local Res. TOTAL Final Engineering Design $0 $0 $199,900 $0 $1,436,690 $1,636,590 Construction Management & Inspection $0 $0 $1,308,910 $0 $0 $1,308,910 AASI Design Integration $118,295 $118,295 Construction* $125,000 $625,000 $16,795,000 $350,000 $2,000,000 $19,895,000 Utility Relocation $90,000 $90,000 Landfill fees $55,000 $55,000 Contingency $0 $0 $1,002,000 $0 $0 $1,002,000 TOTAL ACTIVITY COSTS $125,000 $625,000 $19,305,810 $350,000 $3,699,985 $24,105,795 96.5% TOTAL PROJECT COSTS $125,000 $625,000 $20,182,310 $350,000 $3,699,985 $24,982,295 Estimated Loan Amount: $20,182,310 CRF 2.5% Interest, 20 yr. term 0.06415 Equivalent Uniform Annual Cost (EUAC) $1,294,695 $647,348 Annual Cost w/ 10% coverage $1,424,165 **Whitefish on DEQ Intended Use Plan for Forgiven Principal, Estimated Annual Debt Cost: Whitefish 2019 WWTP Project AGS Reactors - Main Lift Station - Grit Removal - Disinfection - Outfall Line and Diffuser - Renovate Adm Building Project Budget Anticipated Grant Funding and City Cash Contribution SOURCE *VE has identifed $475,209 in potential savings which is reflected in the construction cost total ---PAGE BREAK--- Project: Whitefish WWTP Improvements - 2019 Location: Whitefish, MT Designer: AMCE - Helena Contractor: Swank Enterprises 750 W. Reserve Drive Kalispell, MT 59901 Scheduled Line Section Value 001 01 00 00 Bonds & Insurance 181,422 002 Mobilization & Jobsite Setup 61,727 003 Supervision & Management 381,315 004 Surveying, Staking & Layout 43,600 005 Equipment Rental & Repair 292,660 006 Crane & Operator 284,276 007 Temporary Facilities 64,010 008 General Conditions 536,328 009 Winter Conditions/Snow Removal/Heat 93,876 010 Quality Control Testing 103,550 011 Plant Startup & Functional Testing 78,507 012 Plant Decommissioning 17,682 013 02 41 00 Admin Building Demolition 33,373 014 03 20 00 Rebar Package - Materials Only 307,925 015 Rebar Installation 241,163 016 03 30 00 Site Concrete Structures 41,094 017 Side Stream Lift Station Pad/Walls 18,547 018 Grit Building Foundations 18,050 019 Grit Building Slabs 17,947 020 Grit Vortex & Influent Splitter Structure 103,024 021 Grit Building Topping Slab 7,831 022 Reactor Basin Mat Slab 236,135 023 Reactor Basin Walls 569,186 024 Reactor Basin Effluent Launders/Walks 118,127 025 UV Channels & Foundations 60,776 026 Main Process Building Foundations 28,722 027 Main Process Building Slabs 62,486 028 Main Process Topping Slab 19,437 029 SBB Mat Slab 34,723 030 SBB Walls & Catwalks 105,468 031 Admin Building Concrete 14,893 032 03 41 00 Precast Panel Package - Materials Only 684,520 033 Grit Buildling - Precast Installation 32,496 034 Main Process Building - Precast Installation 68,329 035 05 12 00 Steel & Handrail Package - Materials Only 207,069 036 Grit Building - Steel Installation 21,124 037 Main Process Building - Steel Installation 14,753 038 Reactor Basins - Steel Installation 46,851 039 SBB - Steel Installation 9,306 040 Retaining Wall Handrail Installation 4,474 Scope of Work PRELIMINARY SCHEDULE OF VALUES, 11/19/19 BID ---PAGE BREAK--- 041 07 00 00 Thermal & Moisture Protection Complete 175,519 042 08 11 00 HM Doors, Frames & Hardware 28,853 043 08 33 36 OHC Doors 85,986 044 08 34 83 Floor Hatches 5,828 045 08 43 13 Aluminum Storefronts, Glazing 13,020 046 08 45 00 Translucent Roof and Wall Assemblies 49,030 047 09 20 00 LGS Framing, Gypsum Board & FRP 37,994 048 09 65 00 Floor Coverings 10,320 049 09 90 00 Paint & Coatings 703,802 050 10 00 00 Division 10 Specialties 18,449 051 12 32 16 Casework & Countertops 22,776 052 22 00 00 Plumbing & HVAC Complete 863,934 053 22 13 29 Side Stream Lift Sta. Pumps 48,900 054 26 00 00 Electrical & Communications 1,079,427 055 Electrical Trenching & Ductbanks 64,846 056 31 00 00 Site & Civil Package 057 Site & Civil Mobilization 103,550 058 Excavation Dewatering 51,025 059 Lagoon Decanting 17,767 060 Site Pipe & Process Demolition 134,881 061 Clearing & Grubbing 24,638 062 Site Cut & Fill 158,159 063 Import Fill 201,814 064 Mass Excavation for Rigid Inclusions 79,679 065 12" Ballast/Working Surface 70,782 066 Remove Contaminated Ballast 72,184 067 Excavate, prep, BF for UV channels 23,467 068 Load Transfer Pad for Rigid Inclusions 25,786 069 Reactor Slab Prep 5,216 070 Backfill Reactors 36,720 071 Main Process Foundation Fill Ex/Prep/BF 93,797 072 Main Process Slab Gravels/Prep 18,037 073 Grit Building Fill/Pad 123,223 074 Grit Buildling Foundation Ex/Prep/BF 6,269 075 Grit Building Slab Gravel/Prep 7,197 076 Topsoil 72,178 077 Site Concrete Prep 7,377 078 Gravel Surfacing (Inc. Walking Paths) 32,606 079 Asphalt Sub Base 63,879 080 Asphalt Base 20,919 081 Asphalt Pavement 96,990 082 Guardrails 16,590 083 Retaining Walls 215,603 084 Grade Biosolids Basin 23,789 085 Biosolids Liner Cusion Course 66,551 086 Prep Biosolids Basin for Concrete & Liner 112,816 ---PAGE BREAK--- 087 Biosolids Drying Bed Rehabilitation 088 Remove & Dispose of Organics/Sludge 222,320 089 Remove Sand & Gravel 92,255 090 Extend 6" Perf Pipe 16,482 091 Manholes 12,511 092 3" Minus Import 92,128 093 Fabric & Sand 161,268 094 Valve Replacement 9,156 095 Yard Piping 096 16" Temp Influent Line 61,858 097 Linestop Tap 50,031 098 16" Permanent Effluent Line 64,314 099 4" Temp Sludge 28,539 100 12" Effluent Bypass 30,473 101 6" Domestic Water 31,025 102 60" AR Vault 8,448 103 10" Sewer/Drain & MH Replacement 75,018 104 Bypass Pumping 21,473 105 16" Plant Influent 28,081 106 8" Grit Building Sanitary Service & MH's 17,309 107 Influent Splitter Drains 12,092 108 4" Grit NPW Service 8,779 109 6"/4" Grit W Service 19,994 110 6" Scum w/Cleanout 7,347 111 8"/4" Main Process Sanitary Srvc &MH's 34,503 112 6" SBB Decant 12,598 113 3" TWAS 23,318 114 6"/4" Main Process W Service 20,634 115 16" SBB Overflow 15,214 116 14" TDW & MH's 158,450 117 Effluent Diffuser 99,299 118 3" NPW to Screening 87,513 119 6" NPW 25,360 120 60" AR Vault 8,339 121 18" TWAS 47,608 122 16" TWAS 56,076 123 4" VFA 6,223 124 8" Super 9,034 125 6" DS 37,031 126 6" DS Recirc 16,600 127 Biosolids Control Structure 11,009 128 Biosolids Waste Flow Metering MH 14,279 129 Biosolids Waste Control Valve MH 20,645 130 Low Pressure Air 90,386 131 31 35 26 RPP Liner & Vent System 103,991 132 31 66 00 Rigid Inclusions 899,170 Hayward Baker 133 32 31 13 Chain Link Fencing 15,478 134 32 80 00 Irrigation/Landscaping 156,873 135 33 38 33 Lemna Package (Cover/Baffle/Diffusers/Blowers) 554,281 Lemna/Aerzen 136 40 05 60 Slide/Weir Gates 58,061 Whipps 137 40 15 71 Telescoping Valves 73,862 ---PAGE BREAK--- 138 40 27 00 Process Piping 139 Biosolids Basin 77,794 140 Main Lift Station 78,072 141 Grit Building 300,229 142 Main Process Building 646,613 143 Reactor Basins 268,029 144 SBB Basins 110,367 145 Blower Building 8,494 146 UV 232,738 147 Small Bore Process 308,112 148 40 63 00 PCS Equipment & Flow Meters 74,890 149 41 22 13 Bridge Cranes 55,432 150 41 65 13 Air Compressors 16,928 Gardner Denver 151 43 23 13 Main Lift Station Pumps 247,039 Ghorman Rupp 152 43 23 31 Vertical Turbine Pumps 37,370 Sultzer 153 43 41 43 PE Storage Tanks 37,210 154 43 42 23 Hydro-Pnuematic Tank 7,177 155 46 00 01 AquaNereda AGS System (PO) 2,449,901 AES 156 Installation 225,107 157 46 23 23 Grit Removal System 158,682 Smith & Loveless 158 46 23 63 Grit Washer 156,190 Huber 159 46 23 66 Grit Storage Container 16,350 160 46 33 42 Alum Metering Pumps & Skid 87,113 Prominent 161 46 41 21 Sludge Mixing System 176,015 Vaughan 162 46 66 56 UV Disinfection System 204,757 Trojan 163 1% GRT 203,700 TOTAL $20,370,000 ---PAGE BREAK--- City of Whitefish, Montana Whitefish WWTP Improvements Project Final Draft A. Eckhart 1:2 Draft S.Anderson, P.E. P.Montgomery, P.E. S.Anderson, P.E. 1-2017 SA 1064 N. Warren Helena, Mt 59601 Engineer Owner Sheet Sheet Title Of Date Revision By Project Number Approved By Designed By Checked By Drawn By Plot Scale Revision Project Title CONFIDENTIAL SUBJECT TO NON DISCLOSURE AGREEMENT C-1 Civil Site Plan CIVIL SITE PLAN ---PAGE BREAK--- ---PAGE BREAK--- ---PAGE BREAK--- ADMIN._BLDG 3027' - 0" A1 A2 A3 A4 A5 A6 REPAINT ALL EXISTING CEMENTITIOUS PANELS CORRUGATED METAL AT NEW WALL OH COILING DOOR, 10'W X 10'H ALUMINUM STOREFRONT, X3 OH COILING DOOR, PAINT STEEL DOOR PAINT WALL SCONCE NEW SCONCE 5 A7.1 102a 101b 101a SF.2 SF.1 SF.1 WALL SCONCE PAINT EXISTING METAL COPING A9 A8 A7 PAINT EXISTING METAL COPING. CHECK FOR AND CORRECT LOOSE FASTENERS, RECAULK AS REQUIRED. PAINT EXISTING CEMENTITIOUS WALLS PACK MASONRY COMPOUND WHERE VOIDS EXIST AT THIS JOINT AROUND ENTIRE BUILDING. CAULK ENTIRE JOINT, PAINT. SEE STRUCTURAL FOR ADDITIONAL INFO. REMOVE LOOSE CAULKING FROM ALL VERTICAL JOINTS. RECAULK, PAINT. ADMIN._BLDG 3027' - 0" A1 A2 A3 A4 A5 A6 PAINT EXISTING METAL COPING. CHECK FOR AND CORRECT LOOSE FASTENERS, RECAULK AS REQUIRED. PAINT EXISTING CEMENTITIOUS WALLS PACK MASONRY COMPOUND WHERE VOIDS EXIST AT THIS JOINT AROUND ENTIRE BUILDING. CAULK ENTIRE JOINT, PAINT. SEE STRUCTURAL FOR ADDITIONAL INFO. REMOVE LOOSE CAULKING FROM ALL VERTICAL JOINTS. RECAULK, PAINT. NOTE: THIS ELEVATION CONTAINS LOTS OF PIPING, CONDUIT, ETC. MASK EVERYTHING PRIOR TO PAINTING. ARCHITECT MAY REQUEST SPECIFIC ITEMS BE PAINTED, COORDINATE. A9 A8 A7 PAINT EXISTING METAL COPING. CHECK FOR AND CORRECT LOOSE FASTENERS, RECAULK AS REQUIRED. PAINT EXISTING CEMENTITIOUS WALLS PACK MASONRY COMPOUND WHERE VOIDS EXIST AT THIS JOINT AROUND ENTIRE BUILDING. CAULK ENTIRE JOINT, PAINT. SEE STRUCTURAL FOR ADDITIONAL INFO. REMOVE LOOSE CAULKING FROM ALL VERTICAL JOINTS. RECAULK, PAINT. PAINT EXISTING METAL BASE. CHECK FOR AND CORRECT LOOSE FASTENERS, RECAULK AS REQUIRED. CONFIDENTIAL SUBJECT TO NON DISCLOSURE AGREEMENT City of Whitefish, Montana Whitefish WWTP Improvements Project Final Draft 1:2 Draft 1064 N. Warren Helena, Mt 59601 Engineer Owner Sheet Sheet Title Date Revision By Project Number Approved By Designed By Checked By Drawn By Plot Scale Revision Project Title SAVED:8/29/2019 6:35:30 PM Q:\_Jobs19\05 Whitefish WWTP\5 CD\Drawings\Revit\Whitefish WWTP - CD - SD.rvt Exterior Elevations - Administration Building A4-1 Author Designer Checker 08/27/19 19-05 - 1/8" = 1'-0" A4-1 EXTERIOR ELEVATION - ADMIN BLDG - NORTH 1 1/8" = 1'-0" A4-1 EXTERIOR ELEVATION - ADMIN BLDG - EAST 2 1/8" = 1'-0" A4-1 EXTERIOR ELEVATION - ADMIN BLDG - SOUTH 3 1/8" = 1'-0" A4-1 EXTERIOR ELEVATION - ADMIN BLDG - WEST 4 ---PAGE BREAK--- GRIT SLAB 3042' - 9 1/4" G1 G2 1 A5-1 1 A5-1 INSULATED PRECAST CONCRETE WALL PANELS W/ FLUTED FINISH, TYP. STEEL CANOPY REACTOR BASIN RAILINGS BEYOND STEEL DOOR 10'W X 10'H OH COILING DOOR. TURN DOWN SLAB TO FOOTING, SEE STRUCTURAL CONCRETE REACTOR BASINS. NO FINISH TO WALLS REACTOR BASIN RAILINGS BEYOND CONCRETE REACTOR BASINS. NO FINISH TO WALLS POLE LIGHT 301b 302a TOP OF GRIT PANEL 3060' - 7 1/4" STEEL PLATE TRIM, PAINT SBR SLAB 3029' - 0" 1 A5-1 1 A5-1 SBR PUMP RM. SLAB 3026' - 0" A B C D E F G H J K H.9 INSULATED CONCRETE WALL PANEL, PAINTED INSULATED PRECAST CONCRETE WALL PANELS W/ FLUTED FINISH, TYP. TRANSLUCENT WALL PANELS TRANSLUCENT WALL PANELS X3 STEEL DOOR. 6" SLAB, SEE STRUCTURAL 10'W X 12'H OH COILING DOORS. 10" SLAB, SEE STRUCTURAL 10'W X 10'H OH COILING DOOR METAL COPING, TYP. STEEL CANOPY METAL COPING CORRUGATED METAL WALL PANEL 202b TW.2 TW.2 202a TW.2 203a TW.1 TW.1 TW.1 TURN DOWN SLAB AT THIS OH DOOR, SEE STRUCTURAL PANELS BELOW GRADE EXTENDED TO FOOTING. SHOWN FOR REFERENCE. STEEL DOOR. 6" SLAB, SEE STRUCTURAL TOP OF ELEC. PANEL 3049' - 0" TOP OF SBR PANEL 3055' - 6" 6' - 6" 8' - 0" WALL SCONCE PER ELEC. MOUNT 12" ABOVE TOP OF DOOR FRAME, TYP. BASIN WALL BEYOND, NO FINISH STEEL PLATE TRIM, PAINT, TYP. CONFIDENTIAL SUBJECT TO NON DISCLOSURE AGREEMENT City of Whitefish, Montana Whitefish WWTP Improvements Project Final Draft 1:2 Draft 1064 N. Warren Helena, Mt 59601 Engineer Owner Sheet Sheet Title Date Revision By Project Number Approved By Designed By Checked By Drawn By Plot Scale Revision Project Title SAVED:8/29/2019 6:35:31 PM Q:\_Jobs19\05 Whitefish WWTP\5 CD\Drawings\Revit\Whitefish WWTP - CD - SD.rvt Exterior Elevations A4-2 SD Designer Checker 08/27/19 19-05 - 1/8" = 1'-0" A4-2 EXTERIOR ELEVATION - NORTH 1 1/8" = 1'-0" A4-2 EXTERIOR ELEVATION - SOUTH 2 ---PAGE BREAK--- 2 1 GRIT SLAB 3042' - 9 1/4" 3 A5-1 3 A5-1 2 A5-1 2 A5-1 3 4 5 6 7 8 INSULATED PRECAST CONCRETE WALL PANEL W/ FLUTED FINISH, TYP. BASIN RAILINGS, SEE OTHER DISCIPLINES CONCRETE BASIN WALLS, NO ADDITIONAL FINISH INSULATED PRECAST CONCRETE WALL PANEL W/ FLUTED FINISH, TYP. STEEL CANOPY BEYOND RUSTICATION JOINT POST LIGHTS PANELS EXTEND BELOW GRADE TO FOOTINGS, SHOWN FOR REFERENCE. TOP OF SBR PANEL 3055' - 6" STEEL CANOPIES BEYOND METAL COPING METAL COPING SCONCE, 12" ABOVE DOOR FRAME, TYP. TOP OF GRIT PANEL 3060' - 7 1/4" STEEL PLATE TRIM, PAINT 2 1 SBR SLAB 3029' - 0" GRIT SLAB 3042' - 9 1/4" 3 A5-1 3 A5-1 2 A5-1 2 A5-1 3 4 5 6 7 8 INSULATED PRECAST CONCRETE WALL PANEL W/ FLUTED FINISH, TYP. CONCRETE BASIN WALLS, NO FINISH SEE STRUCTURAL FOR ALL STEEL RAILINGS AND STAIRS POLE LIGHT INSULATED PRECAST CONCRETE WALL PANEL, PAINTED, TYP. INSULATED PRECAST CONCRETE WALL PANEL W/ FLUTED FINISH, TYP. METAL COPING, TYP. STEEL CANOPY BEYOND 301a TOP OF ELEC. PANEL 3049' - 0" STEEL CANOPY BEYOND WALL SCONCE, SEE ELEC. STEEL DOOR TOP OF SBR PANEL 3055' - 6" TOP OF GRIT PANEL 3060' - 7 1/4" CONFIDENTIAL SUBJECT TO NON DISCLOSURE AGREEMENT City of Whitefish, Montana Whitefish WWTP Improvements Project Final Draft 1:2 Draft 1064 N. Warren Helena, Mt 59601 Engineer Owner Sheet Sheet Title Date Revision By Project Number Approved By Designed By Checked By Drawn By Plot Scale Revision Project Title SAVED:8/29/2019 6:35:32 PM Q:\_Jobs19\05 Whitefish WWTP\5 CD\Drawings\Revit\Whitefish WWTP - CD - SD.rvt Exterior Elevations A4-3 Author Designer Checker 08/27/19 19-05 - 1/8" = 1'-0" A4-3 EXTERIOR ELEVATION - EAST 1 1/8" = 1'-0" A4-3 EXTERIOR ELEVATION - WEST 2 POLE LIGHT