Bates Elementary School Safe Routes to School Project Two Week Look Ahead: April 5th –April 16th General Project Information: • Project work hours: 7:00 am – 3:30 pm for day work Projected Construction Activities: Week of APRIL 5th • Granite curb & concrete sidewalks at Liberty Hill & Appleton • Re-locate Hydrant • Police details will be onsite to manage vehicle and pedestrian traffic around the work zones. Week of April 16th • Granite curb & concrete sidewalks at Liberty Hill & Appleton • Install Drainage • Police details will be onsite to manage vehicle and pedestrian traffic around the work zones. Issue Date: April 2, 2021 Please visit the Utility Improvement Project Page link at: