WATER IMPROVEMENT PROJECT: WALL STREET, WALL STREET COURT, BERUBE ROAD, OBER STREET, AND RAWLINS STREET Two Week Look Ahead: 1/29/2024– 2/9/2024 General Project Information: • Project work hours: 7:00am – 4:00pm for day work (except as noted) 9:00pm – 5:00am for night work (if needed) Projected Construction Activities: Week of 1/29/2024 • The Contractor will continue installing water services to residences on Purchase Street, Berube Road, and Wall Street Court. • Water shutdown scheduled for Monday 1/29/2024 on Purchase Street and Henry Street. Notices will be delivered to affected properties. • The Contractor will tie in Henry Street existing water main to newly installed water main. • Water shutdown on Ober Street. Notices will be delivered to affected properties Week of 2/5/2024 • The contractor will begin drain and sewer work on Purchase Street Issue Date: January 25, 2024 Please visit the Project webpage on the Engineering Department Website: http://www.salem.com/city-engineer