← Back to Salem

Document Salem_doc_c69f3c4eb4

Full Text

Columbus Ave Seawall Reconstruction Project Permitting Status Document Updated: 12/6/21 Permit Duration Submitted Received Comments MEPA Certificate 3 months 9/15/21 12/15/21 Completed: MEPA certificate posted on project webpage Conservation Commission 2 months tbd 2/15/22 simultaneously submitted Army Corp of Engineers 4 months tbd 4/15/22 simultaneously submitted Chapter 91 6 months tbd 8/15/22 Assume submit as soon as con comm permit received color code: estimated actual  Assume permitting signatures by September 15, 2021  tbd = to be determined  Assumes no major issues with permitting or appeals. Schedule is estimated. Kimberley Driscoll Mayor DAVID H. KNOWLTON, P.E. CITY ENGINEER/DPS DIRECTOR CITY OF SALEM SALEM, MASSACHUSETTS ENGINEERING DEPARTMENT 98 WASHINGTON STREET, 2ND FLOOR SALEM, MA 01970 Phone: (978) 619-5673