WATER IMPROVEMENT PROJECT: WALL STREET, WALL STREET COURT, BERUBE ROAD, OBER STREET, AND RAWLINS STREET Two Week Look Ahead: 1/8/2024– 1/19/2024 General Project Information: • Project work hours: 7:00am – 4:00pm for day work (except as noted) 9:00pm – 5:00am for night work (if needed) Projected Construction Activities: Week of 1/8/2024 • The Contractor will continue installing water main on Purchase Street and Berube Road. • The Contractor will pressure test and disinfect water main on Purchase Street Week of 1/15/2024 • The Contractor will begin installing water main on Wall Street Court. • The Contractor will pressure test and disinfect water main on Berube Road and Wall Street Court. • The Contractor will begin installing water services to residences on Purchase Street, Berube Road, and Wall Street Court. Issue Date: January 9, 2024 Please visit the Project webpage on the Engineering Department Website: http://www.salem.com/city-engineer