Bates Elementary School Safe Routes to School Project Two Week Look Ahead: April 26th –May 7th General Project Information: • Project work hours: 7:00 am – 3:30 pm for day work Projected Construction Activities: Week of APRIL 26th • Adjust Manhole Castings Liberty Hill & Appleton • Pave and Temporary Line Striping Liberty Hill and Appleton • Police details will be onsite to manage vehicle and pedestrian traffic around the work zones. Week of MAY 3rd • Landscaping • Final Striping and Signage • Police details will be onsite to manage vehicle and pedestrian traffic around the work zones. Issue Date: April 26, 2021 Please visit the Utility Improvement Project Page link at: