Full Text
Bates Elementary School Safe Routes to School Project Two Week Look Ahead: October 19th – October 30th General Project Information: • Project work hours: 7:00 am – 3:30 pm for day work Projected Construction Activities: Week of October 19th • Install drainage at Appleton St. and Liberty Hill Ave. • Installation of granite curb and concrete sidewalks at Nursey Street and Liberty Hill Ave • Granite curb and concrete sidewalks in-front of Bates School. • Police details will be onsite to manage vehicle and pedestrian traffic around the work zones. Week of October 26th • Install drainage at Appleton St. and Liberty Hill Ave. • Installation of granite curb and concrete sidewalks at Nursey Street and Liberty Hill Ave • Installation of granite curb and concrete sidewalks in-front of Bates School. • Police details will be onsite to manage vehicle and pedestrian traffic around the work zones. Issue Date: October 19, 2020 Please visit the Utility Improvement Project Page link at: