WATER IMPROVEMENT PROJECT: WALL STREET, WALL STREET CT., BERUBE ROAD, OBER STREET, AND RAWLINS STREET Two Week Look Ahead: 12/25/2023– 1/5/2024 General Project Information: • Project work hours: 7:00am – 4:00pm for day work (except as noted) 9:00pm – 5:00am for night work (if needed) Projected Construction Activities: Week of 12/25/2023 • The Contractor will continue installing water main on Purchase Street Week of 1/1/2024 • The Contractor will install new valves on Rawlins and Purchase Street and will continue installing water main on Purchase Street • A water shutdown will be planned, additional notification will be provided to affected projects. Issue Date: December 20, 2023 Please visit the Project webpage on the Engineering Department Website: http://www.salem.com/city-engineer