*Note: DOT section complete as of 9/24. Estimated 1.5 weeks to complete remaining scope of the job (will not interfere with DOT section)* Week of October 05 • Contractor will replace gas services • Contractor will perform gas connections • Police details to be on site to manage traffic around work zones Liberty Hill Ave, Appleton St, Nursery St Gas Main Replacement Project • Contractor will install new gas main • Contractor will replace gas services • Police details to be on site to manage traffic around work zones Week of September 28 Project work hours: 7am – 3:30pm for day work Two Week Look Ahead: Projected Construction Activities: General Project Information: September 28 - October 09