Full Text
HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- COMPLETED TASKS 1. Topographic Survey (Field Work Only) 2 G h i l I i i 2. Geotechnical Investigation 3. Schematic Design, Layout & Detailing REMAINING TASKS REMAINING TASKS 1. Design Development Plans and Details 2. Construction Documents & Specifications 3. Public Bidding Process 3. Public Bidding Process 4. Construction Administration SCHEDULE 1. Construction Documents Complete May 15th 2. Construction Bids Due June 7th 3. Construction Start July 1st 4. Substantial Completion September 30th HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- OPTION A HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013 ---PAGE BREAK--- OPTION B HUNTRESS Sports BERTRAM FIELD RENOVATION April 9, 2013