Full Text
*Project should be complete by Friday, 10/9* Week of October 12 N/A Liberty Hill Ave, Appleton St, Nursery St Gas Main Replacement Project • Contractor will perform gas connections • Police details to be on site to manage traffic around work zones Week of October 05 Project work hours: 7am - 3:30pm for day work Two Week Look Ahead: Projected Construction Activities: General Project Information: October 05 - October 16