← Back to Redmo, ND

Document Redmond_doc_e40f3c1746

Full Text

Appendix E: The Unfunded Buildout Plan 187 Appendix E: The Unfunded Buildout Plan DOWNTOWN PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 12 Regional Trail Interchange Improvements 520 Trail 520 Trail Sammamish River Trail and Bear Creek Trail Improve the intersection of three regional trails to reduce safety hazards and add capacity for bicycles and pedestrians. Build new bridge, preferably at height of trails on north side of Leary Way bridge. Coordinate with project 167 Leary Way bridge widening. 13 Redmond Town Center To Marymoor Trail Connection Redmond Town Center To Marymoor Trail Connection Bear Creek Trail at Redmond Town Center Marymoor Park Construct nonmotorized bridge from Bear Creek Trail and Redmond Town Center to Marymoor Park underneath east side of SR 520 bridge over the Sammamish River 119 Avondale Way Extension Avondale Way Extension Redmond Way at Avondale Way NE 76th Street at 168th Avenue NE Construct a new north/south connection between Redmond Way and NE 76th Street. Improvements include one lane in each direction, sidewalks, bicycle lanes, utilities, street lights, trees, signs, and stormwater treatments. The unfunded Buildout Plan includes capital improvements needed for Redmond to complete its long-range transportation system, but which do not currently have identified sources of City funding for the 2013-2030 timeframe. There are a number of regional projects important to the long-range transportation system also included on this list. Please refer to Chapter 6 Regional Transportation for more information on the timeline and status of funding for these projects. With 223 capital improvements, the unfunded portion of the Buildout Plan serves as a guide for completing Redmond’s transportation system. Included in this list are potential system improvements (capacity projects that benefit the overall transportation system) that could move to the Transportation Facilities Plan if funding becomes available. In addition, there are candidate projects for the pedestrian, bicycle, targeted safety, and preservation programs. The candidate projects for potential program funding are not a complete list but include those needed projects that have been specifically identified by the community or through a separate approved plan. As Redmond evolves and travel needs of the community develop, revisions to the Buildout Plan will be needed and new capital improvements are expected to be added.Unfunded Buildout Plan projects are listed in numerical ordergrouped by location: Downtown, Overlake, Marymoor Village and the remaining neighborhoods. The numbers are for the purpose of locating projects on the maps and do not reflect a priority order. Table 18. Downtown projects ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 188 Figure 62. Unfunded Buildout Plan – Downtown ¯ Downtown Education Hill 166th AVE NE NE 80th ST REDMOND WAY NE 85th ST 160th AVE NE NE 83rd ST LEARY WAY 161st AVE NE 164th AVE NE BEAR CREEK PKWY CLEVELAND ST NE 79th ST NE 90th ST 170th AVE NE 159th PL NE RED-WOOD RD NE 169th AVE NE 170th PL NE 337 180 334 226 249 249 278 277 269 250 221 176 280 373 335 185 209 359 220 124 184 296 183 13 192 182 371 326 249 170 186 202 168 120 195 303 122 335 12 167 294 121 119 196 209 Marymoor Park 0 0.2 0.1 Miles Note: projects shown are conceptual only; actual alignments may vary. Neighborhoods Waterbodies Parks City Limit Projects Unfunded Buildout Plan – Downtown N ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 189 DOWNTOWN PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 120 Brown Street Woonerf Brown Street Redmond Way Bear Creek Parkway In conjunction with the Downtown Park, construct a street designed primarily for pedestrians and bicycles, allowing business access but no on-street parking or significant vehicle movements. This woonerf will have a slow design speed, with pedestrians and bicyclists provided priority over vehicles within the roadway and design elements including narrow roadway lanes, special paving treatments, pedestrian amenities, low impact development techniques, public art, lighting, and utilities. 121 Gilman Street Woonerf Gilman Street 164th Avenue NE Redmond Central Connector Construct a street designed primarily for pedestrians and bicycles, allowing business access but no significant vehicle movements. This woonerf will have a slow design speed, with pedestrians and bicyclists provided priority over vehicles within the roadway and design elements including narrow roadway lanes, special paving treatments, pedestrian amenities, low impact development techniques, public art, lighting, and utilities. 122 165th Ave NE Extension 165th Avenue NE Extension Redmond Way Cleveland Street Construct a new north/south connection between Redmond Way and Cleveland Street, realign the NE 79th Street connection to Redmond Way. Improvements include intersection improvements, one lane in each direction, sidewalks, bicycle lanes, utilities, street lights, trees, signs, plaza space, and stormwater treatments. 124 NE 76th Street Ped Improvements NE 76th Street Leary Way 170th Ave NE Improve NE 76th St from Leary Way to 170th Ave NE to create a lively and active street. This pedestrian supportive street would include 1 through lane in each direction, parking, sidewalks, street lights, pedestrian amenities, storm drainage, utility relocation and easements. This improvement project could also include light rail transit depending on timing and final alignment. Table 18. Downtown projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 190 DOWNTOWN PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 167 Leary Way Reconfig- uration Leary Way West Lake Sammamish Parkway 159th Pl NE Reconfigure Leary Way Sammamish River Bridge and widen street from West Lake Sammamish Parkway to 159th Place NE. Improvements would include 2 through lanes in each direction, left turn lanes, lighting, transit amenities, pedestrian bridge on north side and right of way. Coordinate with project 12, bicycle and pedestrian bridge project. 168 170th Place NE Widening 170th Pl NE (Bear Creek Parkway Extension, east) Redmond Way Avondale Way Widen and reroute 170th Place NE from Redmond Way to Avondale Way. Improvements would include 2 through lanes in each direction, left turn lanes, sidewalks, street lights, storm drainage, and right-of-way and easements. 170 158th Ave NE Extension 159th Ave NE Redmond Way NE 83rd St Construct new 159th Ave NE from Redmond Way to NE 83rd St. Improvements include 1 through lane in each direction, parking, sidewalks, street lights, pedestrian amenities, transit stop amenities, storm drainage, right-of-way and easements. 176 West Lake Sammamish Parkway & Leary Way Intersection Improvements and 520 Regional Trail Crossing West Lake Sammamish Parkway at Leary Way Intersection modification. Construct either a multilane roundabout or double left turn lanes (WLSP southbound to Leary Way eastbound) and add a lane on Leary Way from West Lake Sammamish Parkway to the bridge over the Sammamish River. Construct a grade-separated crossing for SR 520 Trail. The trail crossing across West Lake Sammamish Parkway that connects the end of the 520 Regional Trail to the Sammamish River Regional Trail. 180 NE 85th Street Midblock Crossing 85th Street between 161st Ave NE and 164th Ave NE With the Post Office site moving, remove existing right turn lane and add a mid- block crossing with curb bulbs connecting existing and future interior pathways. 182 SR 520 Trail Lighting 520 Trail Sammamish River Trail 148th Ave NE/ City Limits As a transportation facility, lighting is necessary to allow use of the trail, especially during peak hours in the winter months. Provide lighting and consider other elements such as reflective delineators or fog lines. Table 18. Downtown projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 191 DOWNTOWN PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 183 Sammamish River Trail Lighting Marymoor Sammamish River Trail 520 Trail NE 51st St This trail has a unique need for lighting - the trail exists in lieu of a sidewalk on West Lake Sammamish Parkway. Sidewalks in the City are typically lit, meaning that pedestrians in this corridor do not receive the same level of service. As a transportation facility, lighting is necessary to allow use of the trail, especially during peak hours in the winter months. Provide lighting and consider other elements such as reflective delineators or fog lines. 184 Sammamish River Trail North Lighting Sammamish River Trail 520 Trail NE 90th St As a transportation facility, lighting is necessary to allow use of the trail, especially during peak hours in the winter months. Provide lighting and consider other elements such as reflective delineators or fog lines. 185 Bear Creek Trail Widening Bear Creek Trail 520 Trail Union Hill Road Provide an east west route through Downtown for through cyclists by widening the trail to 12 to 14 feet with good sight lines and limited curve radii. As a transportation facility, lighting is necessary to allow use of the trail, especially during peak hours in the winter months. Provide lighting and consider other elements such as reflective delineators or fog lines. 186 159th Place Sidewalk 159th Pl NE Bear Creek Parkway Leary Way Provide interim concrete sidewalk including curb, gutter, and storm as applicable. 192 NE 88th Street Sidewalk NE 88th Street 166th Ave NE 172nd Ave NE Construct sidewalk on one side of roadway including curb, gutter, and storm as applicable. 195 165th Ave NE Sidewalk 165th Ave NE NE 83rd St NE 80th St Construct sidewalk on west side roadway including curb, gutter, and storm as applicable to fill in sidewalk gap. 196 Avondale Way Sidewalk Avondale Way 170th Ave NE Bear Creek Trail Replace heavily degraded sidewalk. Install sidewalk with planter strip up to the Bear Creek Trail, including landscaping. 202 Grasslawn Trail Grasslawn Trail West Lake Sammamish Way Redmond Central Connector Complete difficult connection between Grass Lawn Neighborhood and Redmond Central Connector and Sammamish River Trail by constructing trail from Old Redmond Road and West Lake Way headed east, through a cantelevered bridge under Redmond Way and over 154th Ave, and then to the Redmond Central Connector. Include storm facilities as applicable. Table 18. Downtown projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 192 DOWNTOWN PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 203 Old Redmond Road Cycle Track Old Redmond Road West Lake Sammammish Parkway West City Limits Provide cycle tracks over existing bicycle lanes. Provide storm drain access. 209 Education Hill Bike Boulevard 171st Avenune, NE 88th St, 172nd Ave NE, NE 80th St 100th Street Redmond Way Construct bicycle boulevard treatments such as bicycle related wayfinding signage and channelization, and median islands. 220 160th Avenue NE Shared Lane Markings 160th Avenue NE Cleveland Street NE 90th St Add shared lane markings to roadway, indicating proper positioning for cyclists along bike route. 221 161st Avenue NE and Bear Creek Parkway Bike Signal 161st Ave NE at Bear Creek Parkway Add bicycle signal treatment enabling cyclists to continue on Heron Rookery Trail with access to regional trails. Signal does not allow through vehicular movements, which would be allowed only for bicyclists. 226 Transit Center Bicycle Station Near the Downtown Transit Center (NE 83rd St at 161st Ave NE) Construct a bicycle station to serve the Downtown Transit Center and the Downtown Urban Center central downtown location. A bicycle station includes, covered, enclosed, and secure access bicycle parking that may be staffed during operating hours. The cost is a place holder to coordinate with existing businesses to combine space for bike station. 249 Flashing Beacon Upgrade Flashing Beacon Upgrade: System- wide project Upgrade smart studs at 4 locations: 1) 161st, 87th to 90th; 2) and 3) 83rd, 161st to 164th near Transit Center; and 4) Bear Creek Park Way at 75th. 250 Redmond Way & Avondale Way Intersection Mods Redmond Way/Avondale Way Remove separated right-turn lane from WB Avondale Way to Redmond Way; at eastern end of Downtown east and west Corridor. Coordinate with Project 116. 269 Bear Creek Parkway & 164th Ave NE Flashing Beacon Bear Creek Parkway at 164th Avenue NE Install flashing beacon at the existing pedestrian crossing from Bear Cr trail. Include center median island on east side of intersection. 277 Bear Creek Parkway & 166th Ave NE Crosswalk Bear Creek arkway at 166th Avenue NE Install crosswalk on west leg, providing access to Bear Cr. trail. Table 18. Downtown projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 193 DOWNTOWN PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 279 Einstein Elementary Crosswalk Enhancement Einstein Elementary School Install flashing beacon on NE 116th St at school crossing. 294 166th Ave NE Bike Connection 166th Avenue 76th Street Redmond Way Construct bicycle lanes. 296 Sammamish River Trail Widening Sammamish River Trail Widening NE 90th Street SR 520 Trail Widen existing hard surface regional trail and improve existing section and construct missing links of parallel soft surface trail. 303 91st Street Connection NE 91st Street NE 90th Street 91st Street/166th Ave Enhance existing roadway along steep slope, adding safety and visibility enhancements for pedestrians and vehicles. Add wayfinding. 326 Cleveland Street East Cleveland Street 164th Avenue NE 166th Avenue NE Improve Cleveland Street to a pedestrian- friendly Main Street. Improvements include one through lane, parking, and sidewalk in each direction, mid-block crossings, street lights, utilities, stormwater treatments, public art, bicycle racks, pedestrian amenities, street furnishing, trees, traffic and wayfinding signs, and realignment of street at eastern and western ends to improve traffic flow. 334 Downtown Redmond Light Rail Station Construct a light rail station on the East Link line, including station platforms and and amenities including art, high quality pedestrian access and bicycle parking. Integrate with existing amenities such as the Redmond Central Connector and Heron Rookery Park. 337 Redmond Downtown Transit Center Pickup/Dropoff Zone NE 83rd Street Convert existing on-street parking spaces to a pickup/dropoff zone for transit riders on NE 83rd Street. Include 15 minute parking zone markings and signage. Table 18. Downtown projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 194 Table 18. Downtown projects (continued) DOWNTOWN PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 359 166th Avenue NE Streetscape 166th Avenue NE NE 85th Street NE 104th Street Improve 166th Avenue NE to a pedestrian- friendly street. Improvements include widened sidewalk and one through lane in each direction, center left turn lane and bike lanes, pedestrian amenities, transit amenities, utilities, street lights, stormwater, and LID. Add pedestrian crossings coordinated with bus stops. 371 Redmond Way Widening Redmond Way 168th Avenue NE 164th Avenue NE Add second westbound lane and parking on the north side of Redmond Way between 168th Avenue and 164th Avenue. Project would include one travel lane, on-street parking, sidewalk, right-of-way, utilities and streetscape improvements. 372 Phases 1 & 2 SR 520 Active Traffic Management SR 202 I-405 Add variable speed limits and variable message signs. 373 SR 520/ West Lake Sammamish Parkway – Eastbound off ramp Improvements West Lake Sammamish Parkway Eastbound off ramp Construct either a multilane roundabout or exclusive right turn lane at the ramp terminal. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 195 ¯ 42 372 182 366 259 48 3 68 59 286 56 57 51 2 285 335 49 346 318 172 62 288 289 181 312 313 290 314 310 372 311 26 376 375 374 9 4 40 43 343 345 342 341 348 247 293 284 287 262 260 148th AVE NE NE 40th ST 156th AVE NE NE 24th ST BEL-RED RD BEL-RED RD 0 0.25 0.125 Miles Note: projects shown are conceptual only; actual alignments may vary. Neighborhoods Waterbodies Parks City Limit Projects Figure 63. Unfunded Buildout Plan – Overlake Unfunded Buildout Plan – Overlake N ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 196 OVERLAKE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 2 SR 520/148th Interchange Overlake Access Ramp and Trail Connection Within WSDOT Limited Access Overlake Access Ramp 148th Avenue NE 152nd Ave NE Construct a second eastbound off ramp at 148th Avenue NE. This ramp will go under 148th Avenue NE, terminate at the east side of 148th Avenue NE with a roundabout, and connect the Overlake Access Street and NE 28th Street west of 152nd Avenue NE. Improvements along the ramp include two lanes on the ramp, walls, shoulders, stormwater, utilities, street lights, and a multi-user trail connecting the SR 520 eastbound on ramp with the roundabout. Coordinate with project #315, the Overlake Access Street and project 520 Trail Grade Separation at 148th Avenue NE. 3 SR 520/148th Interchange Overlake Access Ramp and Trail Connection: The Trail Improvement Portion 148th Avenue NE SR 520 EB Ramp NE 29th Place Modify channelization and signals, and provide wide multi-use trail that is separated from the roadway on the east side of 148th Ave NE from the eastbound SR 520 on ramp to the SR 520 Trail at the westbound SR 520 off ramp at NE 29th Place (148th Ave NE bridge over SR 520). Design to accomodate future grade separation project at 148th Avenue NE and NE 29th Place. Coordinate with the Overlake Access Ramp project, 4 SR 520 Regional Trail Grade Separation at 148th Ave NE SR 520 Trail 148th Avenue NE SR 520 Trail Grade separate SR 520 Trail at 148th Avenue NE. 9 NE 40th St & 520 Trail Interim Ped Improvements NE 40th Street at SR 520 Ramps (N side) Construct interim improvement with raised median pedestrian refuge island with push button on NE 40th St along 520 Trail route; curb bump- outs at WB on-ramp; “Yield to Pedstrian” signage. Table 19. Overlake projects ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 197 OVERLAKE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 26 520 BRT SR 520 NE 40th Street SR 202/ Redmond Way In advance of the future light rail alignment to SE Redmond from the Overlake Transit Center Station, develop an alignment or a bus rapid transit corridor with needed right- of-way acquisition and roadway construction. This BRT corridor alignment needs to be compatible with the future light rail infrastructure. Construct layover facilities in Downtown Redmond. 40 Bel-Red Road & 148th Ave NE Turn Lanes Bel-Red Road at 148th Avenue NE Work with the City of Bellevue to add additional capacity in the vicinity of this intersection by creating eastbound and westbound dual left turn lanes at Bel-Red Road and 148th Avenue NE, adding a third northbound through lane on 148th Avenue NE starting south of Bel-Red Road and adding a northbound right-turn lane at Bel-Red Road and 148th Avenue NE. 42 148th Ave NE Multiuse Trail 148th Avenue NE Paved, Shared-Use Path NE 29th Pl Old Redmond Road Provide a wide (12-feet) multi-use trail on the east side of 148th Avenue NE from NE 29th Place to Old Redmond Road. This trail can expand upon the existing sidewalk to accommodate both pedestrians and bicyclists. 43 148th Ave NE & NE 31st St Intersection Improvements 148th Avenue NE at NE 31st Street Signalize and modify intersection to improve safety and traffic operations. Relocate pedestrian crossing at 3300 block to this signal. 48 152nd Ave NE Safety Enhancement 152nd Avenue NE 24th Street 31st Street Rechannelize road to a three lane section where possible and adjust signal phasing to provide protected left turns at this high pedestrian collision location. Coordinate project with storm water holding facility project. It is a near term interim improvement. Table 19. Overlake projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 198 OVERLAKE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 49 152th Ave NE Main Street South of NE 24th Street 152nd Avenue NE NE 20th Street NE 24th Street Implement a multi-modal pedestrian corridor concept on 152nd Avenue NE from NE 20th Street to NE 24st Street to create a lively and active signature street in the Overlake Village. The cross section for the improvements would include 1 through lane in each direction, turn lanes as necessary, on-street parking and pedestrian and bicycle facilities. Other improvements include storm drainage, LID, street lighting, pedestrian amenities, transit amenities, right-of-way, easements, and utilities. 51 156th Ave NE Multiuse Trail 156th Avenue NE Multi-use Trail NE 40th St NE 51st St Provide a wide (12-feet) multi-use trail on the east side of 156th Avenue NE from Bel-Red Road to NE 51st Street. This trail can expand upon the existing sidewalk to accommodate both pedestrians and bicyclists. Coordinate construction with Project 366. 56 NE 40th St Rechannelization Segment I NE 40th Street 148th Avenue NE SR 520 Within existing right-of-way and easements, resize vehicular lanes and add bike lanes in both directions. Improvements include two vehicular lanes in each direction, one turn lane, bike lanes and sidewalks on both sides, stormwater treatments, and street lights. Locations of existing curbs and sidewalks remain the same. Coordinated with 57. 57 NE 40th St Streetscape Segment I NE 40th Street 148th Avenue NE SR 520 Add bike lanes on both sides. Improvements include two vehicular lanes in each direction, one turn lane, bike lanes and sidewalks on both sides, streetscape including gateway wayfinding and art elements, stormwater treatment, utilities, street lights, right-of-way and easement acquisition. Coordinated with 56. Table 19. Overlake projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 199 OVERLAKE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 59 NE 40th St Rechannelization Segment III NE 40th Street 156th Avenue NE 163rd Avenue NE Within existing right-of-way, resize vehicular lanes and add bike lanes in both directions. Improvements include two 10 foot vehicular lanes in each direction, one turn lane, bike lanes and sidewalks in both directions, and streetscape, stormwater treatment, utilities, and street lights. Locations of existing curbs and sidewalks remain the same. Coordinated with 60. 62 NE 40th St Streetscape Segment IV NE 40th Street 163rd Avenue NE Bel-Red Road Add bike lanes in both directions. Improvements include one 11 feet vehicular lane, 5.5 feet bike lane, and 8.5 feet sidewalk in both directions, one turn lane or median, trees, stormwater treatments, utilities, street lights, and right-of-way acquisition, and streetscape including gateway wayfinding and art elements. Coordinated with 64. 68 Bel-Red Road Bicycle and Pedestrian Improvements Bel-Red Road NE 30th Street NE 40th Street Widen Bel-Red Rd from NE 30th St to NE 40th Street. Improvements include bike lanes, pedestrian path, street lights, right-of-way and easement acquisition. 172 150th Avenue NE Bike Improvements 150th Avenue NE NE 51st St NE 40th St Fill in gaps in bicycle facility network on 150th Avenue NE from NE 51st Street to NE 40th Street in both directions, and improve curve radius to allow for truck movements through existing chokepoint. Widen roadway 6’ to west and build retaining walls. Include shared lane markings at edges of new 13’ wide lanes. 181 NE 31st Street Light Rail Station Access NE 31st St 148th Ave NE SR 520 Trail/ Overlake Village Bicycle- Pedestrian Bridge Allow public access to future Overlake Village Light Rail Station and future pedestrian bridge across 520 by acquiring right-of-way or acquiring easement northwest of SR 520. Enhance pedestrian facilities. 182 SR 520 Trail Lighting 520 Trail Sammamish River Trail 148th Ave NE/ City Limits As a transportation facility, lighting is necessary to allow use of the trail, especially during peak hours in the winter months. Provide lighting and consider other elements such as reflective delineators or fog lines. Table 19. Overlake projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 200 OVERLAKE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 247 Bel-Red & NE 30th Street Intersection Improvements NE 30th St and Bel-Red Road Coordinate with City of Bellevue to revise intersection signalization and channelization to improve pedestrian and bicycle access and allow northbound left-turn movements between Bel-Red Road and Microsoft campus. 259 East Link Phase I Seattle to Downtown Redmond Light Rail Transit (LRT) Corridor As part of the East Link Phase I, extend light rail from Bellevue to Overlake Transit Center Station along SR 520, including track, overhead electric wires, utilities, and stormwater. 260 Overlake Transit Center Light Rail Station Overlake Transit Center Light Rail Station Construct a light rail station on the East Link line, including station platforms and and amenities including art, high quality pedestrian access and bicycle parking. Coordinate with Projects 6 to expand the walk and bike shed for the station. 262 Overlake Village Light Rail Station Overlake Village LRT Station Construct a light rail station on the East Link line, including station platforms and and amenities including art, high quality pedestrian access and bicycle parking. Coordinate with Project 5 to expand the walk and bike shed for the station. 284 152nd Midblock Crossing Mid-Block Crossings Provide a mid-block crossing on 152nd Avenue NE between NE 20th Street and NE 24th Street to improve pedestrian accessibility. 285 NE 24th Street Access Management NE 24th Street 148th Avenue NE Bel-Red Road Implement more stringent access management along NE 24th Street from 148th Avenue NE to Bel-Red Road to improve efficiency and safety in the corridor. 286 148th Avenue NE Access Management 148th Avenue NE NE 20th Street NE 36th Street Implement more stringent access management along 148th Avenue NE from NE 20th Street to NE 36th Street to improve efficiency and safety in the corridor. Table 19. Overlake projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 201 OVERLAKE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 287 148th Ave NE Pedestrian Overpass 148th Ave NE Grade Separation Pedestrian overpass Provide a grade-separated pedestrian overpass that crosses 148th Avenue NE in the vicinity of 22nd street. 288 151st Avenue NE South 151st Avenue NE NE 20th Street NE 24th Street Construct new 151st Avenue NE between NE 20th Street and NE 24th Street. Refer to the Overlake Neighborhood Plan for more details. Coordinate with the Overlake Village South Study. 289 NE 22nd St, West NE 23rd St, West Construct new NE 22nd Street from 148th Avenue NE to 152nd Avenue NE and design the street as a local access street using pedestrian supportive design with on-street parking and one through lane in each direction. Major street connections would be signalized. 290 NE 22nd St, East NE 23rd St, East Construct new NE 22nd Street from 152nd Avenue NE to Bel-Red Road and design the street as a local access street using pedestrian supportive design with on-street parking and one through lane in each direction. Major street connections would be signalized. 293 156th Avenue NE & NE 31st Street Turn Lane 156th Ave NE and NE 31st St Construct an additional WB left-turn lane. 310 150th Avenue NE Connection 150th Ave NE 26th Street NE 24th Street Construct Access Street in accordance with Overlake Village Design Standards, including 1 travel lane, parking lane and sidewalk in each direction. 311 151st Avenue NE Connection Segment II 151st Avenue NE NE 27th Street NE 28th Street Construct neighborhood street in accordance with Overlake Village Design Standards, including 1 travel lane,parking lane, cycle track, and sidewalk in each direction as well as an urban pathway trail. Table 19. Overlake projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 202 Table 19. Overlake projects (continued) OVERLAKE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 312 151st Avenue NE Connection Segment I 151st Avenue NE NE 24th Street NE 27th Street Construct neighborhood street in accordance with Overlake Village Design Standards, including 1 travel lane, parking lane, cycle track, and sidewalk in each direction as well as an urban pathway trail. 313 NE 26th Street Connection NE 26th Street 152nd Avenue NE Overlake Access Ramp Terminus Construct Access Street in accordance with Overlake Design Standards, including 1 travel lane, parking lane and sidewalk in each direction. 314 NE 27th Street Connection NE 27th street 152nd Avenue NE Overlake Access Ramp Terminus Construct Access Street in accordance with Overlake Village Design Standards, including 1 travel lane, parking lane and sidewalk in each direction. 318 NE 40th Street Sidewalk Widening 40th Street SR 520 148th Avenue NE Widen sidewalk on both sides of street to meet pedestrian modal corridor standards 335 East Link Phase II Connect to existing East Link light rail line and extend from Overlake Transit Center Station to Downtown Redmond Station along SR 520 and the Redmond Central Connector, including track, overhead electric wires, utilities, and stormwater. Consider light rail maintenance facility needs. 341 150th Avenue Mid- Block Cossing North 150th Ave NE 3800 block Construct a mid-block crossing with flashing beacons on 150th Avenue NE in the vicinity of NE 38th Court. 342 150th Avenue NE Mid- Block Crossing South 150th Ave NE 3700 Block Construct a mid-block crossing with flashing beacons on 150th Avenue NE near NE 36t Street. 343 Microsoft 520 Trail Access Points Provide access points to and from 520 Trail. 345 156th Avenue NE and NE 45th Street Intersection Improvement Extend the existing northbound left turn at 156th Avenue NE and NE 45th Street. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 203 OVERLAKE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 346 NE 28th Street to Bel-Red Road Ped. and Bike Connection NE 28th Street 156th Ave NE Bel-Red Road Provide a hard surface trail connecting NE 28th Street to Bel- Red Road. Acquire public pedestrian and bike easement on NE 28th Street to access Bel-Red Road at the intersection of NE 30th Street and Bel-Red Road. 348 156th Avenue Mid- Block Crossing South of NE 40th Street Construct a signalized mid-block crossing between NE 31st Street and NE 36th Street, utilizing existing median as a pedestrian median. Coordinate crossing with existing transit stops. 366 156th Trail South 156th Avenue NE Bel-Red Road NE 40th Street Intend to provide a high comfort bicycle facility along 156th Avenue NE. Expand the existing 8-foot wide sidewalk to a 12-foot wide multiuse trail on the east side of 156th Avenue NE from Bel-Red Road to NE 40th Street. Coordinate construction with Project 51.. 372 Phases 1 & 2 SR 520 Active Traffic Management SR 202 I-405 Add variable speed limits and variable message signs. 375 Bel-Red Road Widening between NE 20th Street and NE 24th Street Bel-Red Road NE 20th Street NE 24th Street Widen Bel-Red Rd from NE 20th Street and NE 24th Street. Improvements include 2 through lane in each direction, a center turn lanes, bike lanes, curb, gutter, sidewalks, street lights and storm drainage. 376 NE 31st St Bike Lanes (Construction) NE 31st St 152nd Ave NE 156th Ave NE Build bicycle lanes along NE 31st Street from the NE 36th Bridge over SR 520 to 156th Avenue NE. Table 19. Overlake projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 204 Unfunded Buildout Plan – Marymoor Village Figure 64. Unfunded Buildout Plan – Marymoor Village Note: projects shown are conceptual only; actual alignments may vary. Neighborhoods Waterbodies Parks City Limit Projects 395 394 392 14 384 390 97 401 335 398 386 379 391 378 403 237 381 406 396 393 380 377 387 383 385 405 389 400 388 402 404 399 397 382 Marymoor Park 333 244 140 134 133 SE Redmond NE 70th ST REDMOND WAY NE 65th ST NE 68th ST NE 67th ST E LK SAMMAMISH PKWY 174th AVE NE 173rd AVE NE NE 176th AVE NE Neighborhoods Waterbodies Parks City Limit Projects N ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 205 Table 20. Marymoor Village projects MARYMOOR VILLAGE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 14 East Lake Sammamish Trail Connection East Lake Sammamish Trail Redmond Central Connector NE 70th Street Provide grade separated trail through the SR 520/SR 202 Interchange area along the planned light rail alignment, connecting East Lake Sammamish Trail and Redmond Central Connector. Provide access to the planned Southeast Redmond light rail station.(see RZC Appendix 8A) 97 East Lake Sammammish Parkway East Lake Sammamish Parkway Redmond Way 187th Ave NE Widen East Lake Sammamish Pkwy from Redmond Way to 187th Ave NE. Improvements include 1 through lane in each direction, left turn lanes where needed, bike lanes, curb, gutter, sidewalks, street lights, storm drainage, underground power, and right-of-way. (Also shown on page 205) 133 Redmond Way and East Lake Sammamish Parkway Intersection Improvements Redmond Way at East Lake Sammamish Parkway At Redmond Way / E Lake Sammamish Pkwy, convert NB triple left turns (on ELSP) to 2 left turns and thru to better spread traffic between the three lanes; Construct 2nd SB thru lane from 180th to ELSP. Coordinate with project 244. 134 NE 70th St and 176th Ave NE Truck Movement Enhancement NE 70th Street at 176th Avenue NE Improve the intersection geometry and traffic control for trucks and traffic operations at NE 70th St / 176th Ave NE (Note: coordinate with Sound Transit because East Link Draft EIS has proposed signalizing this intersection). Coordinate with Southeast Redmond Light Rail Station Area Transportation Study. 140 Redmond ITS Improvements Citywide Install ITS improvements to improve traffic operations and safety. Improvements include traffic signal controller update, detection system, traffic CCTV, signal communications, signal head update, signalized crosswalk and pedestrian detection system, and battery backup system. 237 68th St Sidewalk NE 68th St 180th Ave NE 185th Ave NE Complete missing sidewalk on both sides of NE 68th Street where missing. 244 180th Ave NE & Redmond Way Crosswalk Modifications 180th Ave NE at Redmond Way At Redmond Way/ 180th Ave NE, remove the diagonal crosswalk and move to the east/west legs; improve crosswalk on south leg with pedestrian refuge. Coordinate with project 133. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 206 MARYMOOR VILLAGE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 333 Southeast Redmond Light Rail Station Construct a light rail station on the East Link line, including station platforms and and amenities including art, high quality non-motorized access, bicycle parking, and vehicle access to the station area. Construct a large parking facility to intercept East King County vehicle commuters, effectively utilizing this station as the terminus station of the line for vehicle parking, reducing impacts on Downtown Redmond and the Downtown Redmond terminus station. 335 East Link Phase II Connect to existing East Link light rail line and extend from Overlake Transit Center Station to Downtown Redmond Station along SR 520 and the Redmond Central Connector, including track, overhead electric wires, utilities, and stormwater. Consider light rail maintenance facility needs. 377 173rd Ave NE Woonerf 173rd Ave NE Marymoor Park boundary NE 67th St Construct woonerf-style local access facility (see RZC Appendix 8A) 378 173rd Ave NE Connection 173rd Ave NE NE 67th St NE 70th St Construct collector arterial (see RZC Appendix 8A) 379 174th Ave NE Connection 174th Ave NE NE 67th St NE 70th St Construct connector street (see RZC Appendix 8A) 380 174th Ave NE Woonerf 174th Ave NE Marymoor Park boundary NE 67th St Construct woonerf-style local access facility (see RZC Appendix 8A) 381 175th Pl NE Woonerf 175th Pl NE NE 68th St NE 70th St Construct woonerf-style local access facility (see RZC Appendix 8A) 382 176th Ave NE Retrofit – LW Tech Segment 176th Ave NE NE 65th St LW Tech north property line Retrofit collector arterial (see RZC Appendix 8A) 383 NE 64th Wy Woonerf NE 64th Wy Marymoor Park boundary 177th Ave NE Construct woonerf-style local access facility (see RZC Appendix 8A) 384 NE 65th St Retrofit NE 65th St Marymoor Park boundary East Lake Sammamish Parkway Retrofit collector arterial (see RZC Appendix 8A) 385 NE 66th Way Woonerf NE 66th Wy 177th Ave NE 178th Pl NE Construct woonerf-style local access facility (see RZC Appendix 8A) Table 20. Marymoor Village projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 207 MARYMOOR VILLAGE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 386 NE 67th St Retrofit – West Segment NE 67th St 173rd Ave NE 176th Ave NE Retrofit collector arterial (see RZC Appendix 8A) 387 NE 67th St Retrofit – East Segment NE 67th St 176th Ave NE 177th Ave NE Retrofit collector arterial (see RZC Appendix 8A) 388 NE 67th St Woonerf NE 67th St Marymoor Park boundary 173rd Ave NE Construct woonerf-style local access facility (see RZC Appendix 8A) 389 NE 68th St Woonerf NE 68th St Marymoor Park boundary 173rd Ave NE Construct woonerf-style local access facility (see RZC Appendix 8A) 390 NE 68th St Connection NE 68th St 173rd Ave NE 177th Ave NE Construct connector street (see RZC Appendix 8A) 391 NE 69th St Woonerf NE 69th St 175th Pl NE 177th Ave NE Construct woonerf-style local access facility (see RZC Appendix 8A) 392 NE 70th St Retrofit NE 70th St 173rd Ave NE Redmond Way Construct collector arterial street (see RZC Appendix 8A) 393 Redmond Way non-motorized crossing near Southeast Redmond Light Rail Station Redmond Way between WB SR 520 on- ramp and NE 70th St North side of Redmond Way South side of Redmond Way Consistent with the Southeast Redmond Neighborhood Plan, provide a non- motorized crossing of Redmond Way that increases route directness to/from the Southeast Redmond light rail station and minimizes potential conflicts with vehicles. 394 Marymoor Subarea Perimeter Trail – North Segment Marymoor Park perimeter Southwest corner of Marymoor Subarea East Lake Sammamish Trail Construct 14-foot-wide hard-surface path with adjacent 6-foot-wide soft- surface path (see RZC Appendix 8A) 395 Marymoor Subarea Perimeter Trail – South Segment Marymoor Park perimeter Southwest corner of Marymoor Subarea Marymoor Connector Trail Construct 12-foot-wide hard-surface path with 2-foot-wide hard-surface shoulders (see RZC Appendix 8A) 396 176th Ave NE Extension 176th Ave NE NE 70th St Redmond Way Construct connector street with right- in, right-out access at Redmond Way to function as a third entrance to the subarea. 397 177th Ave NE South Woonerf 177th Ave NE Marymoor Park boundary NE 63rd St Construct woonerf-style local access facility (see RZC Appendix 8A) 398 NE 63rd St Connection NE 63rd St 177th Ave NE 180th Pl NE Construct connector street (see RZC Appendix 8A) Table 20. Marymoor Village projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 208 N MARYMOOR VILLAGE PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 399 180th Pl NE Connection – South Segment 180th Pl NE East Lake Sammamish Parkway NE 63rd St Construct connector street consistent with design approved as part of the Alexan Marymoor apartments project 400 180th Pl NE Connection – North Segment 180th Pl NE NE 63rd St NE 65th St Construct local access street consistent with design approved as part of the Alexan Marymoor apartments project 401 177th Ave NE Connection 177th Ave NE NE 63rd St NE 68th St Construct connector street (see RZC Appendix 8A) 402 178th Pl NE Woonerf 178th Pl NE NE 65th St NE 66th Wy Construct woonerf-style local access facility (see RZC Appendix 8A) 403 179th Ave NE Woonerf 179th Ave NE Marymoor Park Boundary NE 65th St Construct woonerf-style local access facility (see RZC Appendix 8A) 404 176th Ave NE Retrofit - 67th Segment 176th Ave NE LW Tech north property line NE 67th St Retrofit collector arterial (see RZC Appendix 8A) 405 176th Ave NE Retrofit – Middle Segment 176th Ave NE NE 67th St NE 68th St Retrofit collector arterial (see RZC Appendix 8A) 406 176th Ave NE Retrofit – North Segment 176th Ave NE NE 68th St NE 70th St Retrofit collector arterial (see RZC Appendix 8A) Table 20. Marymoor Village projects (continued) ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 209 g Note: projects shown are conceptual only; actual alignments may vary. 42 182 374 368 204 335 178 201 203 372 142 75 68 209 161 214 359 183 366 185 67 184 296 51 97 143 74 48 65 3 113 370 215 59 172 211 66 62 286 297 395 77 220 156 124 187 248 56 179 227 158 361 91 90 64 354 285 321 291 13 236 98 192 88 219 217 346 49 148 197 394 207 237 205 218 384 390 208 357 136 234 216 228 202 198 364 181 194 199 130 196 213 249 12 206 120 229 210 144 303 121 380 322 400 Marymoor Park Lake Sammamish 259 14 2 57 268 318 392 275 295 375 190 336 371 15 288 326 289 397 365 225 398 312 386 170 186 379 313 167 290 376 391 314 378 168 195 403 191 316 310 145 294 381 85 396 393 119 377 382 387 147 383 122 385 222 404 389 311 388 402 405 399 223 406 401 189 26 26 309 188 Neighborhoods Waterbodies Parks City Limit Projects Figure 65. Unfunded Buildout Plan – neighborhoods Unfunded Buildout Plan – Neighborhoods See Downtown map, page 185 See Overlake map, page 192 See Marymoor Village map, page 201 ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 210 NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 15 SR 520 Terminus Enhancements Union Hill Rd at Avondale Rd Union Hill Road and 178th Pl NE Avondale Road and Avondale Way Provide a flyover ramp from westbound NE Union Hill Road to southbound SR 520; provide an Avondale Road flyover ramp over NE Union Hill Road with ramps to NE Union Hill Road. Provide grade separated crossing of Avondale Road for Bear Creek Trail extension. Complete bicycle lane network in project area for at grade portion. Complete sidewalks in project area. Enhance pedestrian and bicycle crossing safety through intersection improvements for at grade section. Improve HOV and freight access through the project area. 27 SR 520 & SR 202 Off Ramp Improvement SR 520 and SR 202/ Redmond Way Improve the geometry of Eastbound SR 520 off ramp at Redmond Way to reduce queue blocking. 44 Redmond Way & 148th Avenue NE Intersection Improvements Redmond Way at 148th Avenue NE Widen intersection to separate the northbound share through and left turn lane to have dual left turn lanes and two through lanes to improve traffic flow. 64 NE 40th St Rechannelization Segment V NE 40th Street Bel-Red Road West Lake Sammamish Parkway Within the existing right-of-way, provide one vehicular lane, 5.5 to 6 feet bike lane, and 5.5 to 6 feet sidewalk in each direction. A 5.5 feet planter is optional in the eastbound direction. This optional planter requires resizing the width of vehicular lanes to 11 feet. Other improvements include street scape, stormwater treatments, utilities, and street light. Coordinated with 62. 65 NE 51st Street New Sidewalk NE 51st Street 158th Avenue NE West Lake Sammamish Parkway Complete missing segments of sidewalk on the southside of NE 51st St from 158th Ave NE to West Lake Sammamish Pkwy. 66 NE 51st St Bike Lanes NE 51st Street 148th Avenue NE 154th Avenue NE Provide bicycle lanes on NE 51st Street in both directions from 148th Avenue NE to 154th Avenue NE. Install additional bike signage and pavement markings in existing bike lane between 154th Avenue NE and West Lake Sammamish Parkway. Table 21. Neighborhood projects ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 211 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 67 NE 51st St Rechannelization NE 51st Street 156th Avenue NE West Lake Sammamish Parkway Install additional bike signage and rechannelize roadway to install standard bike lane in the westbound (uphill) direction and implement a shared lane in the eastbound (downhill direction) from 156th Avenue NE and West Lake Sammamish Parkway. 74 160th Ave NE Extension 160th Avenue NE NE 99th Street Red-Wood Road Construct new 160th arterial from current terminus at approximately NE 99th Street north to the intersection with Red- Wood Rd. Modify existing 160th arterial from NE 90th St north to current terminus. Relocate transit service and amenities from Red- Wood Road to 160th Avenue NE. Improvements include 1 through lane in each direction, left turn lanes, bike lanes, curb, gutter, sidewalks, transit amenities, street lights, storm drainage, wetland and stream mitigation, right of way and easement acquisition. 75 NE 116th St Widening Segment II NE 116th Street 167th Place NE 179th Place NE Widen NE 116th St from 167th Place NE to 179th Place NE. Improvements include 1 through lane in each direction, left turn lanes, bike lanes, curb, gutter, sidewalks, equestrian trail, street lights, storm drainage, underground power, right-of-way and easement acquisition. 77 NE 116th St Segment III NE 116th Street (East End) 179th Avenue NE Avondale Rd Widen remaining sections of NE 116th St from 179th Avenue to Avondale Road. Improvements include 1 through lane in each direction, left turn lanes, bike lanes, curb, gutter, sidewalks, equestrian trail, street lights, storm drainage, underground power, right-of- way and easement acquisition. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 212 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 85 Redmond Way Bridge Replacement Over Bear Creek Redmond Way Bear Creek Crossing Avondale Road On Ramp Replace the Redmond Way Bridge over Bear Creek. Improvements include 2 through lanes in each direction on Redmond Way and NE 76th Street, 2 eastbound left turn lanes to NE 76th St, 1 eastbound right turn lane to westbound SR 520 on- ramp, sidewalks, Bear Creek and E Lake Sammamish Trail connections, street lights, storm drainage, right- of-way and easements. The bridge will be designed to accommodate a grade separated connection of Bear Creek Trail underneath the bridge. The bridge should only be replaced when the existing bridge conditions no longer meet federal structural rating requirements. 88 NE 76th Street Widening NE 76th St Avondale Road at northbound on ramp to SR 520 terminus 178th Place NE widen roadway to include three 12’ travel lanes and two bike lanes and 6’ sidewalks, realign roadway to comply with COR minimum horizontal curve radius requirement. At the signalized intersection of Fred Meyer and Target, add crosswalk to west leg, use existing right run drop lane eastbound, re- aligned to account for roadway widening. At intersection of 76th and eastbound 520 ramps add a crosswalk enabling pedestrian and bicycle crossing. Improve transit amenities. 90 NE 76th Street Widening 178th Place to 185th Ave NE NE 76th St 178th Place NE 185th Avenue NE Widen roadway to include a 12’ center turn lane, two 12’ travel lanes and two 5.5’ bike lanes and 6’ sidewalks on both sides of roadway. Coordinate with 91. 91 NE 76th St Rechannelization NE 76th St 178th Place NE 185th Avenue NE Rechannelize roadway to include one 12-foot 2 way left turn lane, one 14’ shared lane in each direction. Coordinate with 90. 96 East Lake Samm. Pkwy and 187th Ave NE Signal East Lake Sammamish Parkway at 187th Ave NE Install new traffic signal. Improvements include southbound left turn lane and reconstruct grade separated trail crossing. Design to accommodate project 97. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 213 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 97 East Lake Sammammish Parkway East Lake Sammamish Parkway Redmond Way 187th Ave NE Widen East Lake Sammamish Pkwy from Redmond Way to 187th Ave NE. Improvements include 1 through lane in each direction, left turn lanes where needed, bike lanes, curb, gutter, sidewalks, street lights, storm drainage, underground power, and right-of-way. 98 187th Ave NE Widening 187th Ave NE East Lake Sammamish Parkway Redmond Way Widen 187th Ave NE from East Lake Sammamish Pkwy to Redmond Way. Improvements include 1 through lane in each direction, left turn lanes, bike lanes, curb, gutter, sidewalks, street lights, storm drainage. 113 192nd Ave NE Extension 192nd Ave NE Extension NE 68th St Union Hill Rd Construct new 192nd Ave NE from NE 68th St to Union Hill Rd. Improvements include 1 through lane in each direction, left turn lanes, bike lanes, sidewalks, street lights, traffic control, storm drainage, right-of-way and easements. 127 NE 95th St and Avondale Realignment NE 95th Street at Avondale Road Intersection re-alignment reduces skew, adds a north leg crosswalk, realigns east/west legs removing split-phasing and provides for north to south U-turns. 129 188th Ave NE and Union Hill Right Turn Lane 188th Avenue NE at NE Union Hill Road Improve the intersection of 188th Ave NE at Union Hill Rd by building northbound exclusive right-turn lane. 130 Avondale Road and 180th Ave Reconfiguration Avondale Road at 180th Avenue NE Intersection reconfiguration to add eastern fourth leg serving Avondale Green subdivision and south leg crosswalk. Intersection also allows for north and south U turns. Includes 1,200 feet of new street connecting to 183rd Court NE. 135 188th Ave NE and NE 65th St Intersection Improvements 188th Avenue NE at NE 65th Street Improve intersection operations and safety at the intersection of 188th Avenue NE and NE 65th Street including but not limited to sight distance and pedestrian crossing. 136 NE 84th St Stormwater Enhancement 188th Avenue NE, 192nd Avenue NE north of NE Union Hill Rod, and NE 84th Street Improve NE 84th Street and portions of 188th Avenue NE, and 192nd Avenue NE north of Union Hill Road to coordinate with a Natural Resources CIP project. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 214 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 142 Evans Creek Trail Extension SE Redmond Trail 188th Ave NE 196th Ave NE south of Union Hill Road Build extension of the Evans Creek Trail. 143 Bear Creek and Evans Creek Trail Extension Along Bear Creek and Evans Creek north of NE Union Hill Road Approx. NE 95th St Union Hill Rd Build extension of the Bear and Evans Creek Trail system. 144 Woodbridge Trail Connection Approx. NE 76th Street 192nd Ave NE Arthur Johnson Park Add trail connections from Woodbridge neighborhood to the SE Redmond Trail (At approximately NE 76th Street). 145 Woodbridge- to-Evans Creek Natural Area Trail Woodbridge- to-Evans Creek Natural Area Trail Evans Creek Trail Evans Creek Natural Area Add a trail from Woodbridge neighborhood to 196th Ave NE and the Evans Creek Natural Area. 147 185th Avenue NE-to-East Lake Sammamish Park Pedestrian Trail 185th Avenue NE Redmond Way East Lake Sammamish Parkway Add pedestrian trail from south terminus of 185th Ave NE to E. Lake Sammamish Parkway and East Lake Sammamish Trail. 148 180th Ave NE “Pedestrian Spine” Pedestrian spine 178th Place NE NE 70th Street Construct a “Pedestrian Spine” or corridor that connects the future light rail station and Southeast Redmond retail commercial area and other transit facilities in the vicinity. 154 Avondale Rd and Avondale Way Safety and Access Improvements Avondale Road at Avondale Way Realign intersection replacing slip lane with a pedestrian bulbout with bike lane continuing through in existing location. Add right turn only lane to replace slip lane. Install crosswalks linking bus stops together. 156 Willows Road Widening North Willows Road NE 116th St NE 124th St Widen Willows Road from NE 116th St to NE 124th St. Improvements include 2 through lanes in each direction, left turn lanes, bike lanes, curb, gutter, sidewalks, transit amenities, street lights, storm drainage, underground power, right-of-way and easement acquisition. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 215 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 158 West Lake Sammamish Parkway Interim Improvements West Lake Sammamish Parkway NE 51st St Bel-Red Road Provide interim nonmotorized facilities by striping the west side of West Lake Sammamish Parkway between NE 51st Street and Bel-Red Road to include a bicycle lane and pedestrian path. Provide additional signage and street pavement markings for bicycles on the east side of the street. 161 Redmond Woodinville Road Widening Red-Wood Road 160th Ave NE Extension NE 124th St Widen Red-Wood Rd from intersection with new 160th Ave NE Extension near the Puget Power trail north to NE 124th St. Improvements include 1 through lane in each direction, left turn and extended right turn lanes if appropriate, access management, bike lanes, curb, gutter, sidewalks, street lights, storm drainage, underground power and right- of-way acquisition. 162 Redmond Woodinville Road and NE 109th St Turn Lane Red-Wood Road at NE 109th St Add a northbound right-turn lane. 178 Willows Road Widening South Willows Road NE 90th St NE 116th St Widen Willows Rd from NE 90th St to NE 116th St. Improvements include 2 through lanes in each direction, center left turn lanes/medians, bike lanes, curb, gutter, sidewalks, transit amenities, pedestrian crossings, street lights, storm drainage, underground power, right-of-way and easement acquisition. 187 154th Place NE Widening and Safety Enhancement 154th Pl NE Redmond Woodinville Road NE 116th St Widen roadway to provide shoulder(s) wide enough to accommodate pedestrians and bicyclists. 188 152nd Ave NE Staircase 152nd Ave NE at Redmond Way Construct staircase between Redmond Way and 152nd Avenue NE. Add bike runnel. 189 151st Avenue NE Staircase 151st Ave NE at Redmond Way Construct staircase between Redmond Way and 151st Ave. Add bike runnel. 190 NE 95th Street Sidewalk NE 95th St Willows Road 151st Ave NE Construct sidewalk on south side of roadway including curb, gutter, and storm as applicable. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 216 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 191 151st Avenue NE Sidewalk 151st Ave NE NE 95th St NE 92th St Construct sidewalk on east side of roadway including curb, gutter, and storm as applicable. 194 164th Ave NE Sidewalk 164th Ave NE NE 95th St NE 99th St Construct sidewalk on roadway including curb, gutter, and storm as applicable. 197 Idylwood Park and Transit Safety and Access Project West Lake Sammamish Parkway Bel-Red Road NE 40th St Construct sidewalk on north side of roadway. Include curb, gutter, and storm as applicable. 198 154th Ave NE Sidewalk 154th Ave NE NE 85th St NE 90th St Construct 5’ wide sidewalk on west side of 154th Ave. Include curb, gutter, and storm as applicable. 199 NE 87th Street Sidewalk NE 87th St Willows Road 148th Ave NE Construct sidewalk over existing ditch with existing 10’ of ROW. Include curb, gutter, and storm as applicable. 201 Redmond Central Connector Segment III Redmond Central Connector NE 100th St North City Limits Complete the third segment of the Redmond Central Connector, including regional trail and aesthetic enhancements. 204 PSE Trail Improvements Puget Sound Energy Trail Sammamish River Trail Avondale Road Construct a hard surface regional trail with parallel soft surface trail. 205 172nd Ave NE Trail 172nd Ave NE NE 111th St NE 116th St Construct a hard surface regional trail with parallel soft surface trail. 206 171st Bike Boulevard 171st Pl NE / 172nd Pl NE 172nd Trail NE 111th Street Construct bicycle boulevard treatments such as bicycle related wayfinding signage and channelization, and median islands. 207 172nd Trail Improvement 172nd Trail 104th Street 172nd Pl NE Construct a hard surface regional trail with parallel soft surface trail. 208 Hartman Park Trail Enhancement 172nd Ave NE 171st Ave NE NE 104th St Construct a hard surface regional trail connection. 210 Trail at Ardmore Improvement Trail at Ardmore NE 24th St 172nd Ave NE Construct a hard surface regional trail with parallel soft surface trail, include design treatments to slow bicycle speeds along trail corridor. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 217 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 211 PSE Trail Enhancement Puget Sound Energy Trail NE 93rd Ct Puget Sound Energy Trail Construct a hard-surface trail linking the existing PSE trail with 93rd Court and northern terminus of 142nd Avenue adjacent to Willows Creek Park through existing easement. Add regional bicycle wayfinding and shared lane markings from the end of the trail at 93rd Court to 132nd Avenue. 213 106th Street Connection NE 106th St Red-Wood Road Sammamish River Trail Construct a trail linking the Sammamish River Trail with 106th Street. Add wayfinding and shared lane markings along 106th Street. Acquire easements. 214 NE 24th Street Rechannelization NE 24th St 172nd Avenue NE West Lake Sammamish Parkway Rechannelize to add bicycle lanes in both directions between West Lake Sammamish Parkway and 180th Avenue NE, and a cross section with an uphill bike lane and a downhill sharrow between 180th Avenue and 172nd Avenue NE/City Limit. Where space exists include on street parking in roadway cross section. 215 180th Avenue NE Sidewalk and Bike Lanes 180th Avenue NE West Lake Sammamish Parkway NE 24th Street Enable nonmotorized connections to Audubon Elementary. Construct sidewalk on west side of roadway. Add bicycle lanes to both sides of roadway. Include curb, gutter, and storm. 216 Idylwood Shared Lane Markings 174th Avenue, 175th Avenue, 28th Street 172 Avenue NE NE 24th Street Add shared lane markings south on 174th Avenue and north on 175th Avenue, and in both directions on 28th Street, indicating proper positioning for cyclists along bike route connecting to 172nd Avenue and 24th Street. 217 151st Ave NE Rechannelization 151st Avenue, 95th Street 90th Street at 151st Avenue Willows Road at NE 95th Street Rechannelize existing roadway to include bicycle lanes on both sides of roadway. 218 Avondale Road/ SR 520 Off Ramp Sidewalk Westbound 520 to NE 76th St off ramp Union Hill Road NE 76th St Provide sidewalk on west side of roadway, including curb gutter and stormwater as applicable. 219 Redmond Way to 142nd Ave NE Bike Blvd 140th Ave NE, NE 84th St, 142nd Ave NE Redmond Way PSE Trail (Planned) Linking up with future Trail through Willows Creek Park, create bike boulevard per Bicycle Facility Design Guidelines. 222 80th Staircase NE 80th Street extension 172nd Ave NE Avondale Way Construct staircase between Redmond Way and 80th Street. Add bike trough/ runnel. ---PAGE BREAK--- Appendix E: The Unfunded Buildout Plan 218 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 223 NE 27th Place Trail Connection NE 27th Place 175th Avenue NE 176th Place NE Construct neighborhood sidewalk connection. 225 152nd Ave NE Vertical Curb 152nd Ave NE NE 60th Street 6400 Block Replace roll up curb with vertical curb, improve sidewalk and create student load/unload zone that provides convenient access for children walking, biking and taking the bus to school. 227 151st Avenue NE Sidewalk 151st Ave NE North of Old Redmond Road End of 151st Ave NE Construct sidewalk on one side of the street. 228 134th Ave NE Sidewalk 134th Ave NE NE 75th St NE 80th St Construct sidewalk on one side of the street. 229 NE 83rd St Sidewalk NE 83th St 132nd Ave NE 134th Ave NE Construct sidewalk on one side of the street. 234 Avondale to Union Hill Rd Sidewalk Avondale Way North of Union Hill Avondale Rd Complete missing sidewalk on east side of Avondale Way north of Union Hill Rd. 236 185 Avenue NE Sidewalk 185th Ave NE NE 68th St NE 62nd Court Complete missing sidewalk on west side of 185th Avenue NE near NE 68th Street, and south of NE 65th Street. 248 148th Ave NE Access Improvements 148th Ave NE, Willows Rd to Redmond Way Locate and construct pedestrian crossing and traffic signal to serve residents and office workers; access to bus stops at 148th Avenue and 87th Street (new Rapid Ride route). 252 156th Ave NE Midblock Crossing 156th Avenue NE (between 45th & 51st) Construct a signalized mid-block crossing between NE 45th Street and NE 51st Street, utilizing existing median as a pedestrian median. Coordinate crossing with existing transit stops. 253 Bear Creek Trail & NE Union Hill Road Modifications Bear Creek Trail Union Hill Road Raise trail to enable use by avoiding flood water from Bear Creek. Remove trail surface, and install boardwalk. Raise enough to meet bike height needs. 268 Red-Wood Road Shoulder Red-Wood Road (SR 202) NE 109th Street 116th Street NE Construct 2,180’ of paved shoulder along west side. Shift centerline to allow continuous striped shoulder on both sides for pedestrians and cyclists. 271 West Lake Sammamish Parkway & NE 24th Street Intersection Regrading W Lake Sammamish Pkwy at NE 24th Street Improve sight-distance by re-grading Northwest corner of intersection. ---PAGE BREAK--- Appendix F: Design Guidance 219 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 275 Redmond Way Sidewalk South Redmond Way 140th 145th Construct missing sidewalk on south side; solutions include extensive retaining walls or structured steel walkway w/railing. Improve transit stop amenities. 276 185th Ave NE & NE 68th Street Ped Improvements 185th Avenue NE at NE 68th Street Install traffic control, pedestrian crosswalks, and rain garden for employees in the area. 321 Willows Road Rechannelization Willows Road South of PSE Trail NE 90th Street Rechannelize to provide southbound bicycle lane. 278 Bear Creek Parkway & 168th Ave NE Crosswalk Bear Creek Parkway at 168th Avenue NE Install crosswalk on west leg, providing access to Bear Creek trail. 280 NE 80th Street & 165th Avenue NE Intersection Modification NE 80th Street at 165th Avenue NE Install pedestrian crossing on east side with sidewalk “bulb-out” into street. 282 151st Avenue NE & NE 90th Street Traffic Signal 151st Avenue NE at NE 90th Street Install traffic signal and provide for pedestrian crossings with bump-outs. Install Rapid Ride stop. 291 Bel-Red Road Widening Bel-Red Rd West Lake Sammamish Parkway NE 40th Street Widen Bel-Red Rd from West Lake Sammamish Pkwy to NE 40th St. Improvements include 2 through lane in each direction, left turn lanes, bike lanes, curb, gutter, sidewalks, street lights and storm drainage. 295 150th Avenue NE and 520 Trail Nonmotorized Connection 150th Avenue NE NE 60th Street NE 51st Street Construct hard surface nonmotorized connection between 150th Avenue NE and a planned 520 Trail access point north of NE 51st Street (on private property). The alignment of this nonmotorized connection follows the alignment of existing path on Microsoft’s private campus. This project would be coordinated with Microsoft and not require ROW or easements. 297 152nd Avenue NE Bicycle Connection 60th Street, 152nd Avenue, 68th Street Old Redmond Road 156th Avenue Construct bicycle treatments such as bicycle related signage and channelization. 300 NE 116th Street & 154th Place NE Staircase 116th Street 154th Pl Construct staircase between 116th Street/Red-Wood Road and 154th Place. Add bike runnel. ---PAGE BREAK--- Appendix F: Design Guidance 220 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 309 8400 Block Trail 8400 block Redmond Central Connector Purchase right-of-way and construct pedestrian and bicycle trail connecting local streets to future Redmond Central Connector. 322 Red-Wood Road Street Sidewalk Red Wood Road south of 109th NE 109th Street Around NE 107th Street Construct 420’ sidewalk along west side using cantilevered structure (similar to Bel- Red Road near Microsoft campus). 316 NE 84th Street Sidewalk NE 84th Street 140th Avenue NE 142nd Avenue NE Construct sidewalk to provide access to signal at Redmond Way. Ensure sidewalk facilitates safe pedestrian movements to and from intersection. Include curb, gutter, and storm treatments. 338 Bike Parking Facilities in Bear Creek Park and Ride Lot Provide secure bike parking facilities at the Bear Creek Park and Ride. Work with King County Metro. 340 148th Avenue NE and Old Redmond Road Intersection Improvement Extend the eastbound right turn lane by increasing length and channelization. 344 NE 51st Street and 154th Place NE Westbound Left-Turn Lane NE 51st Street 154th Ave NE Provide a westbound left-turn lane on NE 51st Street at the intersection of NE 51st and 154th Place NE. Improvement includes right-of-way acquisition. 354 NE 116th Street Shoulder Widening NE 116th Street Sammamish River 154th Place NE Widen the shoulder from the Sammamish River to 154th Place NE for cyclists and pedestrians. 357 NE 87th Street Staircase and Sidewalk Connect NE 87th Street near 148th Avenue to 87th Street and 147th Avenue with a combination of staircases and sidewalk. 358 Avondale Road and 180th Avenue NE Crossing Enhancement Add crosswalk and two ADA ramps to the south leg of the intersection. 364 NE 76th Street Extension - Segment 2 NE 76th Street 188th Avenue NE 192nd Avenue NE Construct new NE 76th St from 188th Ave NE to 192nd Ave NE. Improvements include 1 through lane in each direction, left turn lanes or medians to create a 3 lane section, bike lanes, sidewalks, street lights, traffic control, storm drainage, right-of-way and easements. Consider roundabout at 185th Ave and 76th St. ---PAGE BREAK--- Appendix F: Design Guidance 221 Table 21. Neighborhood projects (continued) NEIGHBORHOOD PROJECTS Project ID Project Title Location Project Limits: From Project Limits: To Description 365 NE 73rd Street Extension - Segment 2 NE 73rd Street 188th Avenue NE 192nd Avenue NE Construct new NE 73rd St from 188th Avenue NE to 192nd Avenue NE. Improvements include 1 through lane in each direction, left turn lanes, bike lanes, sidewalks, street lights, traffic control, storm drainage, right-of-way and easements. 370 NE 116th St Widening Segment I Phase II NE 116th St Red-Wood Road 167th Pl NE Complete NE 116th St from Red-Wood Road to 167th Place NE. Improvements include one through lane in each direction, left turn lanes, bike lanes, curb, gutter, sidewalks, equestrian trail, street lights, storm drainage, underground power, right-of-way, and easement acquisition. Improvements coordinate with project # 356: the construction of a roundabout at NE 116th Street and 162nd Avenue NE. Phase I is project ID # 76. 374 New SR 520 Auxiliary Lane at Various Locations SR 520 I-405 West Lake Sammamish Parkway Construct new auxiliary lanes at the following locations: 1) eastbound between the 148th Ave NE interchange and the NE 40th St interchange; 2) eastbound from NE 51st Street on-ramp to Westlake Sammamish Parkway off- ramp; and 3) westbound from Westlake Sammamish Parkway on-ramp to NE 51st Street off-ramp. ---PAGE BREAK--- Appendix F: Design Guidance 222 This page left intentionally blank.