Full Text
C I T Y OF P U Y A L L U P City Clerk’s Office 2016 Clarks Creek Restroom Replacement Project Opening Date: October 27, 2016 2:00 p.m. Company Base Bid Total CCT Construction, Inc. $145,830.20 Boettcher & Sons, Inc. $177,284.89 Nova Contracting, Inc. $222,311.74 NorTec Construction, Inc. $226,397.83 D.W. Excavating, Inc. $241,613.20 Five bids were received and opened at 2:00 p.m. in the Puyallup City Hall Council Chambers, at 333 South Meridian, Puyallup, Washington. Staff Present: Patrick Sheehy PE, CJ Corpuz, CIP Inspector, Sarah Harris, Director, Parks & Rec, and Mary Winter, City Clerk Engineer’s Estimate: $165,899.63