Question and Answer #1 Request for Quote For Otsego Lake County Park Beach Upgrades Otsego County, Michigan BID 2025-06 Questions from: : 2025.04.29 Questions as posed: Otsego County’s Answers: 1. Please see Amendment #1 for change to Section II stating question answers provided no later than September 2, 2025 at 4:30p.m. 2. Please see Amendment # 1 for addition of Section II #11 regarding bonding requirements. Thank you. Josh Guy General Manager Catskill Remedial Contracting Services, Inc. 1020 E. Grand River Ave., Brighton, MI 48116 1. I notice the deadline for responses to bidders’ questions is 5/9/2025 at 4:30 pm, this is after the bid opening. Are you able to move the response deadline up to before the bid opening, or move the bid opening back to allow bidders to adjust pricing based on responses? 2. Are there any bonding requirements for this project?