Full Text
June 5, 1995 CHANGE ORDER NO. ONE Styner Ave.- LI.D. No. 1 13 The contractor shall perform the following construction staking: 1. Slope staking@ 1 00ft. intervals (midway of 1 00ft. slope staking set by others) 2. Subgrade (50 ft. intervals , 3 across) 3. 1 base aggregate (50 ft. intervals, 3 across) 4. Curb (25' intervals, drops, & radius points) 5. base aggregate (centerline@ 25ft. intervals) 6. Sanitary sewer system location 7. Water main location 8. Storm sewer system location 9. Illumination system location 1 0. Retaining walls location 11. Monument/casings 12. Record/as-built information All staking shall be in accordance with standard practices. Stakes damaged by the Contractor shall be replaced at the Contractor's expense. The project's completion time remains the same. Net increase in contract amount . $ 1 9,500. 00 Original contract amount . . . . . . . . . . . . . 58 9,7 91.90 REVISED CONTRACT AMOUNT $ 6 09,2 91.90 City of Moscow, Idaho President 95-48