CHANGE ORDER CHANGE ORDER NO.: 05 PROJECT: 1912 Moscow High School Historic Renovation- Phase 1 9973 INITIATION DATE: September 10, 2001 CONTRACT DATE: February 21, 2001 PROJECT NO.: TO: Citadel Construction, Inc. I 0 I 03 N. Division, Suite 105 Spokane, W A 99218 Tel: 509/466-2993 Fax: 509/466-4329 Job Site Fax: 208/882-4969 OWNER: City of Moscow P.O. Box 9203 Moscow, ID 83843 Tel: 208/883-7087 Fax: 208/883-7093 ARCIDTECT: Design West Architects 254 E. Main Pullman, W A 99163 TEL. 509/332-3113 FAX 509/332-3327 You are directed to make tbe following changes in tbis Contract l. CPR-28 (PR-13) 2. CPR-29 (PR-15) 3. CPR-35 (PR-16) 4. CPR-36 (PR-17) 5. CPR-41 6. CPR-42 (PR-13b) 7. CPR-45 (PR-20) 8. CPR-46 9. CCD-01 Door hardware modifications $ 1,972.25 Addition of standpipes at First and Second Floors $ 5,740.31 Deletion of unnecessary fire dampers $ (1,066.25) Deletion of temporary lighting in Phase 2 areas $ (482.26) Site regrading . $ 2,228.70 Deletion of door hardware cores and keying $ (707.25) Sidewalk modifications $ 2,259.75 Parking lot subsoil improvements $ 1,265.00 Subsoil improvements at retaining walls (first location) $ 1,000.00 SUBTOTAL $ 12,210.25 Not valid until signed by both Owner and Architect. Signature of Contractor indicates his agreement herewith. including any. adjustment in the contJ:act Sum or contract Time. It is further understood and agreed that this change constitutes compensation in full on behalf of the Contractor and its Subcontractors and Suppliers for all costs directly or indirectly attributable to the changes ordered and for any and all delays, impacts, disruptions, acceierations and/or extensions of time related thereto. No other CO'illpi::nsation shaH be allowed fur the Modiiicauicnls made hc:xwith. "The original Contract Sum $ 1,228,000.00 Net change by previously authorized Change Orders (C.O. $ 39,620.16 The Contract Sum prior to tbis Change Order was $ 1,267,620.16 The Contract Sum will be increased by this Change Order $ 12,210.25 The new Contract Sum including tbis Change Order will be $ 1,279,830.41 The Contract Time will be extended by calendar days by tbis Change Order. Page I of2 2001-45 ---PAGE BREAK--- CONTRACTOR: Citadel Construction, Inc. 10103 N. Division, Suite 106 Spokane, VVA 99218 (Date) End of Document OWNER: CityofMoscow P.O. Box 9203 Moscow, ID 83843 Page 2 of2 ARCIDTECT: Design VVest Architects 254 E. Main Pullman, VV A 99163