January, 27,1999 CHANGE ORDER NO. 1 Project: MOUNTAINVIEW STORM SEWER- Joseph Street to White Avenue Bridge Proj. 108-98 1. ADJUST 8 INCH STORM SEWER An 8 inch storm sewer line, crossing the trench of the new 48 inch pipe, was found to be above our proposed grade. It was necessary to lower a portion of the existing pipe and reconstruct the inlet of one storm sewer manhole. SUBTOTAL. . $1 ,341.25 EXISTING CONTRACT AMOUNT . . . . . . . . . . . . $ 161.414.55 NET CHANGE THIS CHANGE ORDER. . . . . . . . . . . . . . $ 1 ,341.25 REVISED CONTRACT AMOUNT . . • . . . . . . • . . . . . . . . $ 162,755.80 Contractor: Motley - Motley Const. Owner Secretary 99-13