Full Text

Greater Moscow Area Coalition Brownfields Program Site Assessment Process Property Owner Submits Program Application to City Approval of Application by Internal Review Denial of Application by Internal Review Group Contamination Exceeds EPA Threshold Contamination Less Than EPA Accepted Threshold. (No further action required) City Submits Property Approval Form to EPA Site Access Agreement Returned From Property Owner Conduct Phase I Assessment Site Access Agreement Sent Develop Phase I Report Determination of Findings Determination of Findings Denial of Property by EPA Approval of Property by EPA EPA Will Grant Final Approval Prior to Proceeding to Phase II Conduct Phase II Assessment Develop Phase II Report Phase III Cleanup Planning (if applicable) Responsibility Key Property Owner City EPA SHPO Letter Prepared by City* THPO Letter Prepared by City* ESA Letter Prepared by City* SHPO comments prepared by State of Idaho THPO comments prepared by ESA comments prepared by Idaho Deptartment of Fish and Game *