Document Moscow_doc_9a5c7c5135

Full Text

CHANGE ORDER AlA DOCUMENT G701 Distribution to: OWNER ARCHITECT CONTRACTOR FIELD OTHER PROJECT: Moscow Recycling Center (name, address) Moscow, Idaho TO (Contractor): I 0 ȗ 0 0 0 CHANGE ORDER NUMBER: 1 INITIATION DATE: 6/25/93 ARCHITECT'S PROJECT NO: 92035 Fleming Construction 1144 16th Avenue CONTRACT FOR: New Construction Clarkston, Washington 994o3 L CONTRACT DATE: 4/05/93 You are directed to make the following changes in this Contract: See attached summary and supporting documentation. Not vJI!d unlit PiQned hy both thl' Ownt-r Jnd <;iT:n.llurt• oi till' (onlr.H lor rnda.tll'' hrѩ •'!:n'l'nwnt hPn'\\'rth, tndudrn!-: LJ615 "PlșN U-f r - • I · , PROJECT o I H6'tt-cJ vl Ňec'( o" t-l b Vtt-l{­ }1 0-C,(J o I) \ IV /Al--0  CASTELLAW KOM ARCIIITECfS w TOWN SQUARE SID MAIN sr. 1110 Jl! I.E\VlSTON. I.D B)SOI (108) 746-0113 ---PAGE BREAK--- . w z Ǟ O:Cil we Ȑȑ Cll c z 0Ȓ ѠѫѬ I- ўџ wu w z w ȏ Cll њ I z I Cll 0 w ќ a. :5 c I . CITY OF MOSCOW TO p· lE METER. PIPE, AND COt-. ''fl TO MAJN. CONTRACTOR CITY F"E:E. EXIST. CURB .ddž.g) ,Ѫ.1 ,oѤ / 0 I \  ¬ 0 EJQSL_ ASPHALT PAVING TYPICAL 0 0 0 0 COLUMNS PER ARCH (TYP) 1-STORY BLDG FIN. FLR.=70.00 SEE ARCHITECTURAL DRAWINGS fOR ADDITIONAL INFORMATION 0 0 .ncr -'UZ ѣcnwo <(ȓȔȕ uowu Oa:t..•O Q..LJ.,U1..J OIL WATER SEPARATOR (SEE CP-IA FOR AOOTNL INFO) 123456 CATCH BASIN, 57 ѡ· SEWER - 1'\lC SOR J5 Ǡ· P£R roor STREET IVI't l.J-Y'f DL MI'IJ(.. I " vr tt"l.l CONNECTION TO 8( MADE WITH MANUFACTURE (SEE DETAJL) BENCHMARK: D 3" AC (AJ.L ( 2" AC CONSTRUCTION NOT I) PROVIDE 2 HO SLOPE BETWEEN W1 AT NW'L Y COR OF" 2) PROVIDE STAG! ON 'ECOLOGY BLOC 3) CONTRACTOR ћ OUT RETAINING WAt COMMENCING WORK ARCHITECT OF »ff 4) THE STORM Sl BE PREMANUFACTEI 5) CONNECT 4" ǟ WITHOUT OISTUR81N 6) ALIGN 30" OIA DRAINAGE DITCH M MIN COVER 7) ALL DETAILS N SHALL CONFORM T! STANDARD ORAWIIIC 8) PROVIDE 0/W CITY STANDARD 52 9) TENSAR GEOGF THE FACE OF WALl PROVIDE A CONTINI 'CONSEAL' ON EACI NOTCH AND BETW( BLOCK LEAVE ALL TO PROVIDE DR/oiN1 WALL OF 3/4" MIN TO 957. MAX OEĤS 1 0) AJ.L GRADES 11) SEE ARCHITf FOR SITE: DIMENS!I 1 2) ALL PIPING 13) CONTRACTOR STREET PAVING TC MIN DEPTH. CONTI 14) CITY OF MO: INCLUDING THE Mt PAY FEE AND COC PROVIDE FROM TH 15) CONTRACTOR POLE. 16) CITY OF Ѣ0! LABOR AT SEWER PAY F'OR CONNEC' 1 7) AT WEST 51[ LOCATIONS. AT EA' AT DRIVE BY CON' PER CITY STANDAF 18) PROVIDE CL OUTSIDE. NEAR Tl 19) PROVIDE DR UNE O.SFT IN DEl TO THE CATCH Bѝ GRADING PLAN AND UTILITY PLAN TOP OF SEWER MANHOU LOCATED SOUTH OF SW PROPERTY CORNER NElr DRAINAGE DITCH. Rf'-1=2571.30 PROJECT o TOWNSQUARE SIOMAINST. 1210 LEWISTON. lD 83SOl (208) 746-Gt83 SIIEET ---PAGE BREAK--- « ) ®¯Ulm@ ©©lm®l:r°M©lfO@OO 1 1 44 16th Avenue Clarkston. Wash•ngton 99403 Mr. Greg Castellaw CASTELLAW-KOM ARCHITECTS 504 Main St. - Suite 210 lewiston, ID 83501 RE: Moscow Recycling Center Dear Greg: roeneua Cf5onAacloŃ Phone (509) 758-7185 FAX (509) 758-6287 June 22 199.3 The following is a cost breakdown for Change Proposal Request /13: Item Changes to conveyor pit per drawings SC-1, SC and SC-3. 14a ter ial $ 152.00 Tax 8.00 Labor 59.00 Subtotal $ 219.00 OH & Fee @ 25% 55.00 TOTAL ADD $ 274.00 Item 112: 2411 dia. concrete casing in lieu of pipe bollards at grids Dl, El, Fl, F2, & F2.5. Material: Delete pipe bollards Add concrete columns Subtotal Material Tax Labor: Pipe bollards Concrete columns TOTAL DEDUCT $(1,603.00) 546.00 $ 0 57. 00) ( 53.00) .380.00) 479.00 $(1,011.00) ---PAGE BREAK--- Item Provide 'Keystone' retaining wall in lieu of 'Ecology Block' retaining wall. Deduct: Material: Ecology Blocks Geo grid Gravel Footing Labor: Add: Ecology Blocks Geo grid Gravel Footing Deduct Sub to tal Material: Keystone Blocks Geogrid Gravel F oo tin g Labor· Keystone Blocks Geogr id Gravel Footing Add Subtotal Summary: Additional Material Tax Additional Labor Subtotal OH & Fee @ 25% TOTAL ADD 4,537.00) ( 6,351.00) ( 98.00) ( 1,870.00) ( 1,520.00) ( 300.00) $(14,676.00) $ 10,620.00 6,310.00 260.00 7,461.00 1,610.00 650.00 $ 26,911.00 $ 6,204.00 311.00 6,031.00 $ 12,546.00 3,136.00 $ 15,682.00 If you have any questions, please don't hesitate to call. Respectfully Submitted, FLEMING CONSTRUCTION P/7l,,70 Mark A. Fleming Partner ---PAGE BREAK--- CKA CA STELLA W KO M AR CHITE CT S Towne Square 504 Main Street Suite 210 Lewiston, 10 83501 (208) 746-0183 CHANGE PROPOSAL REQUEST Change Proposal Request No.: 2 Project: Moscow Recycling Center Owner: City ofMoscow Contractor: Fleming Construction Date: May 18, 1993 Project No.: 92035 Contract For: New Construction Contract Dated: April 5, 1993 Please submit an ITEMIZED quotation for changes in the Contract Sum and/or Time incidental to proposed modifications to the Contract Documents described herein. THIS IS NOT A CHANGE ORDER NOR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED HEREIN. A copy of this change proposal must accompany all price quotes associated with the changes proposed herein. Copy: Item 1 Item 2 Item 3 Owner ªchitect Contractor Provide structural revisions to conveyor pit as indicated on enclosed drawings SC-1, SC-2, and SC-3. Work shown transfers the forces imposed on the #7 rebar connecting the columns at Grid around the new conveyor pit location. Add/Deduct $ In-lue-of pipe bollards at grids Dl, El, Fl, F2 & F2.5 provide 2ft. diameter concrete casing 4 foot high similar to detail 8/A6. Slope top to shed moisture. Verify actual concrete cover with actual steel column sizes subniitted by building manufacturer. Add/Deduct $ _ Provide 'Keystone' retaining wall in-lue-of 'Ecology Block' retaining wall as described in the enclosed drawings. Concrete cap and removeable railing/fencing at top of wall still to be provided. Provide near vertical batter of wall (I :32). Follow Manufacturer's instructions and recommendations. Add/Deduct $ ---PAGE BREAK--- . . CKA CA STELLA W KO M AR CHITE CTs Item 4 Provide complete cost for Items 1,2 &3 together. Add/Deduct $ ---PAGE BREAK--- . · PQOJѕCT 9 Post-It"' brand rax transmitlal memo 7671 I' of pages ? To A f,j:_ Co. F0b'71t/N'6 Ch/J'Y, DepJHaw-w' ŁJ:U/ Fax * 7 s-B 6 l/ 5 J From {pDž5(p Co. Phone#7t./6 -0 I 8' Fax Ŀ 7 ŀ J 7 1 _ 1Yf'· SLAf> JoiNT Cf/S·'Z. ¨ I - ·2w-o / . tteVIł / I I POl " \ coN©YOf2-. PIT L.O&.A-IION 1'8" Ȏ 11 ---PAGE BREAK--- . . . - ѓ- ' ' it.- ȇȈL· r 10 C...f 1 L,..-tl:SIHȍP ȋVLȌ I . . CONT, ro/-oTD, 'lOt) ȅ · ƾoot:.. /Nro eM. Al' ct..JO _ § Ȋ\.JALLSJ IJSC -ƽ . . . - . . - ) ' . . . . . . . . . 'AOJIC"t • Chy orMOKow looyollD' Ctntar ^ . L 3.t.3.o ļ UJ/ Ľ 1 LIIǂLpeD ľ'iUO l"tiGIIOJǃDŽ· 0 Ȇ . . lJA TE • :nn:lT 4-ao-93 S£-'l tMo.n:cr Ho: o ǀZ03ǁ ---PAGE BREAK--- STANDARD UNIT oo· CORNER UNIT Note: Angled oometa must be fteld split. ALTERNATING COURSES CONSTRUCTION ADHESIVE TO BOND OVERLAPPING CORNER UNITS. I.e. Keystone Kapselll Adhesive CONNECTION BETWeEN 1 SJ AND ALTERNATE CQUBSES OUTLINE OF ALTERNATING COURSES PLACED ABOVE FIRST COURSE LENGTH AND WIDTH OF CORNER UNIT MAY NEED TO BE Rf=l"llf".,::l"\ Aђ DI\"T"T'i!::O • • .ss P.01 n. mformatlot.l •-u.od bor-oiD b Ȅ, w.u s, In<. ao4,., boot of ow knowl•4•. •..,.r&ldy _ ёct no U.lho appl cotln.), -ȃb iiJ-...L Piool do.....m-!ioo or я •uh.I>Uilt ot o. uoo oadito-rof,.ooialhooci•rr..,._;Lil.ilyotlbo-. юHaf E.F. Engineering CONSUL TINCi ENGINEERS 4 RCTAIIIIHC WALl ELEVATION 140SCOW R£CYCUHG CENTER C STRECT AND JACKSON STRECT P.O. BOX 261 I I LEWISlON, IDAHO SJ501 I t.OeA- NOSCOW1 lo.uiO Em (208) 746-`408 1AS1 lilY. `/lO QJDIT CKA NICKITECTS lfl ---PAGE BREAK--- F / PROJECf o o " I Ou 0 1sl¢ - -,ol¤ -4 • .ljlo"-=1 B A t:::LS-v.L;:rtot-1 чш ĺJc-tĻ!Rl ' 11''11 1- · L. .CPƵ-ƶ­ PROJEcr ƷguoJ?== SHEET ---PAGE BREAK--- I I 1: I v t·-L PROJF.Cf o o Ʊ H o suoIJ v I,..U..i{P rJ,--ı Ʋ -t-iDS0o1..Jl I DP.Ha · 1 {pt) i , il c.oijĴJ 11? a' Jl  CASTELLAW KOM ARCIIITECTS ilii 'IUWN SQUARE SIO MAIN ST. !IIZIO 10 IIJSOI (lOll) 7щ111 DATE o SHEET 4-'0!3 DRAWN<> 1 . v PROJECT NO. o '1Ul1s- ---PAGE BREAK--- / PROJECI"  CASTELLAW KOM ARCIUTECfS W TOWNSQUARE 5101\tAINS'f. fllO LEWlSTON, lD S:JSOI (l08)7!1Sl DATE o , DRAWN<> •tzF-W PROJECT NO.<> Ș36 SHEET ---PAGE BREAK--- \ ) ©©OO®lrOOU!J©lrU@OO weneua ceonAadM4 1144 16th Avenue Clarkston, Washington 99403 Phone {509) 758-7185 FAX {509) 758-6287 t1ay 20, 1993 Mr. Greg Castell aw CASTELLAW-KOM ARCHITECTS 504 Main St. - Suite 210 Lewiston, ID 83501 RE: Moscow Recycling Center Dear Greg: , Due to adverse weather conditions and condition of the site, we are requesting an additional 13 calendar days for Substantial Completion on the above referenced project. The days we are requesting additional time for are April 29, 1993 through May 11, 1993. The wet weather had made the site unworkable and we had to shut down all work. If you have any questions, please cal l . Sincerel y, FLEMING CONSTRUCTION )1J, j Mark A. Fleming, Pa&er ---PAGE BREAK--- ®lMJDOO@ ©@±®LiCR3GlJ©tr0@00 rJen,eta/ 75onAack-M 1 t 44 16th Avenue Clarkston, Washington 99403 Phone (509) 758·7185 FAX (509) 758·6287 June 22, 1993 Mr. Greg Castellaw CASTELLAW-KOM ARCHITECTS 504 Main St. - Suite 210 Lew is ton, ID 83501 RE: Moscow Recycling Center Dear Greg: Due to additional adverse weather conditions and condition of the site, we are requesting an additional 26 calendar days for Substantial Completion on the above referenced project. The days we are requesting time for are May 26, 1993 through June 20, 1993. The wet weather had made the site unworkable and we had to shut down all work. If you have any questions, please call. Sincerely, FLEMING CONSTRUCTION t?i:<1i:rf7" Partner