Full Text
November 4, 1996 CHANGE ORDER NO. ONE Project: Drill Cemetery Well Perforate the 16-inch diameter casing to allow the water at the 265 foot level to enter the welL Perforations to be 8 per foot 1/2 in. X 4 for 1 0 feet; from the 260 to 270 foot depth. The original well design did not include allowances for these perforations because the aquifer at that level was not known to exist. Existing contract amount... $229,921.80 Amount of increase for this extra work.. 3 700.00 Revised contract amount $233,621.80 Holman Drilling Corporation: City of Moscow, Idaho: 1 , , i/ I vvt,d - f- "Secretary ! / t-ca 96-57