Full Text
December 3, 1996 CHANGE ORDER NO 1 PROJECT: South 95 Storm Drain Improvements - 1996 Project No. 114-93 1. Replace the sanitary sewer service to Northwest River Supplies, complete, from the building to the main. Their existing service was at the grade of the new storm sewer and had to be raised to allow a flowline over the 30-inch pipe. Added cost. . 1,870.00 2. Re-connect an existing 6-inch diameter storm drain lateral to the business STOVES PLUS - work that had not been shown on the plans . Added cost . . . . . . $ 350.00 3. Replace the edge of Northwest River Supplies' asphalt surfaced parking lot - work not shown on the plans. CONTRACTOR Added cost. Total Added Cost . . . . . . . . . . Original Contract Amount . REVISED CONTRACT AMOUNT CITY: . $ 215.00 $ 2,435.00 74.000.00 $76,435.00 /La Paul C. Agidus, Mayor 96-62