July 2 5, 199 5 CHANGE ORDER NO. 2 Project: Styner Avenue.- L.I.D. No. 1 13 1. Manhole Modifications a. Remove existing sewer manhole bases and reconstruct with new materials. Furnish materials and labor . . . . . . . . . . . . . . . $1 780.00 - b. Existing manhole has no adjustment rings to lower grade. Sawcut top of manhole cone section to meet proposed grade . $ 50.00 2. Repair Unstable Subgrade SUBTOTAL. . . . $1830.00 a. Underground springs have saturated the area around new storm manhole number S-7. It is necessary to do sub -excavation, install a filter fabric and crushed aggregate backfill to stabilize the area for roadway embankment. Furnish materials, labor and equipment . $ 5 10.14 EXISTING CONTRACT AMOUNT $589,79 1.90 NET CHANGE C.O. #1 $ 19,500.00 NET CHANGE TH IS CHANGE ORDER . . $ 2,340.14 REVISED CONTRACT AMOUNT $6 1 1,632.04 City of Moscow, Idaho President Mayor City Clerk 95-64