Full Text
2 0 0 C. D IT I 0 N AlA DOCUMENT G701-2000 Change Order (Instructions on reverse side) PROJECT: City of MOSCOW CHANGE ORDER NUMBER: One Fire Station #ATE: October 28, 2003 PO.:Box 9203 ' MOSCOW, ID 83843 ARCHITECT'S PROJECT NUMBER: 02065 CONTRACT DATE: June 16, 2003 TO CONTRACTOR: CONTRACT FOR: New Construction OWNER 0 ARCHITECT CONTRACTOR 0 FIELD 0 OTHER 0 {Name ti.tid cJdn.ssJOrmond Builders I Inc. Moscow Fire Station #3 PO Box 1814 Idaho Falls, ID 83403-1814 THE CONTRACT IS CHANGED AS fOLLOWS: Refer to Attachment A The original (Contract Sum) §tM'KK!K:i!001l!J!:lX was s llQ,.35J • 0 0 'fhe net change by previously authori7...ed Change Orders s_jLJli} _ The (Contract The (Contract Sum) ooxä:!f:i§å!MJX]jlri<æ will be (increased)ç) (èébythis Change Order in the amount of s."#lc-,53_7 .LOO _ The nevv (Contract Sum) (C){l)Têëm::!tOOx)-induding thls Change ()rder will be s_j _ 8_8B. 0 0 The Contract Time 9viii be (;tP¥«1)t'KM) (unchanged} by_z_e_r_9_ 0 ) Jays. The d.ate of Substantial Completion us of the date of this Change Order therefore is February j 0 1 2 0 0 4 NOTE: This Change O:n:ler does not indude changes in the (_,ontr.act Sum, Contract Time or Cuaranteed r..-taximum Price which have been authorized by Construction Cb:angt Directive fix which the wst or time are in dispute as dcs...::rilx·d in Subparagraph ; . .).SDf AlA Document Azm. Not valid until signed by the Architect, Contractor and Owner_ I The American Institute of Architects 1735 New YorL- rd \AI Washington, 2003_50 I ---PAGE BREAK--- CKA CASTELLAW KOM ARCHITECTS 850 Main Street Lewiston, lD 83 50 I (208) 7 46-0183 Fax (208) 746-7267 Change Order #I Date: October 28. 2003 Attachment A THE CONTRACT IS CHANGED AS FOLLOWS: Item 01: Revise dorm room lavatory fixtures from metering type to non-metering type and add garbage disposal per Ormond Price Change Request No. 0 !-Revise and Add Plumbing Fixtures, dated August I. 2003. $000.00 l!C:.JlJ02: Lower oil/water separator and associated piping to accommodate actual grade conditions and piping slope requirements per Onnond Price Change Request No. 02 Lower Oil Water Separator and Piping. dated August 15,2003. $647.00 Item_()}: Revise the finish on the exterior decorative steel column caps per Castellaw Kom Architects memo dated September 08. 2003 and Ormond Price Change Request No. 03 Revise Steel Collar Finish. dated September 08. 2003. ($263.00) Item OJ: Re-route the cable TV conduit per Castellaw Kom Architects memo dated September 05. 2003 and Ormond Price Change Request No. 04-Revise Ronting for Cable TV. dated September 03. 2003. $895.00 ltem_Q:)_: Add mullions to louvers per Ormond Price Change Request No. 05 -Add Mullions to Louvers, dated October 01. 2003. $707.00 ll>'Ill 06: Provide painted wall banding per Castellaw Kom Architects Color Schedule dated September 2003 (revised October OS. 2(103) and per Ormond Price Change Request No. 06 ´Add -wall Striping in Apparatus Bar Area. dated October 6. 2003. $941.00 ItenlQ_7_: Provide cost savings to revise exterior window glazing from Type I-1 to Type l-2 per Ormond Price Change Request No. 07 Revise Exterior Glass Type. dated October 22. 2003. ($1284.00) Item.o.µ: Upgrade fire hydrant installation per Castellaw Kom Architects Proposal Request No. 01. dated September 30. ¶003 and Onnond memo Proposal Request No. 1 -Fire Hydrant System Tie Rods. dated October 15.2003. $1894.00 Total Contract Sum t·evision: $3,537.00