July, 03, 2001 CHANGE ORDER NO. 1 Proj ect: Street L.I. D. No. 126,127 ,and 128. Proj. 123-97 1. RE-ROUTE SANITARY SEWER LINE Sanitary sewer service on Cherry Street required re-location due to placement of new catch basin (northeast corner). 2. RELOCATE CATCH BASINS SUBTOTAL . $ 371.00 Due to conflicts with a gas line and a water line, two catch basin locations had to be re established by additional excavation and exploration. This work resulted in additional time and backfill material beyond the installation of catch basin item. 3. REMOVE JUNIPERS SUBTOTAL . . . . $ 561.00 A resident in Division I requested additional JUnipers to be removed to allow relocation and construction of his driveway. The resident will be assessed directly for this expense. SUBTOTAL . . . . . . . . $ 207.00 TOTAL . . $ 1,139 EXISTING CONTRACT AMOUNT . . . . $177,821.90 NET CHANGE THIS CHANGE ORDER . . . . . . $ 1,139.00 REVISED CONTRACT AMOUNT $178,960.90 Contractor: Motley- Motley, Inc. 1