July, 03, 2001 CHANGE ORDER NO. 1 Proj ect: Street L.I. D. No. 126,127 ,and 128. Proj. 123-97 1. RE-ROUTE SANITARY SEWER LINE Sanitary sewer service on Cherry Street required re-location due to placement of new catch basin (northeast corner). 2. RELOCATE CATCH BASINS SUBTOTAL . $ 371.00 Due to conflicts with a gas line and a water line, two catch basin locations had to be re­ established by additional excavation and exploration. This work resulted in additional time and backfill material beyond the installation of catch basin item. 3. REMOVE JUNIPERS SUBTOTAL . . . . $ 561.00 A resident in Division I requested additional JUnipers to be removed to allow relocation and construction of his driveway. The resident will be assessed directly for this expense. SUBTOTAL . . . . . . . . $ 207.00 TOTAL . . $ 1,139 EXISTING CONTRACT AMOUNT . . . . $177,821.90 NET CHANGE THIS CHANGE ORDER . . . . . . $ 1,139.00 REVISED CONTRACT AMOUNT $178,960.90 Contractor: Motley- Motley, Inc. 1