Change Order No. One City Hall Carpeting Contract City of Moscow, Idaho - Carpet Mill 1. Additional work was added to the project to include the carpeting of the Police Chief's office, Police Department Conference Room and front hallways Added Cost 1,567.94 2. Additional base covering for the newly carpeted rooms Added Cost 253.75 3. The reception counter in the area previously occupied by code enforcement was included. Added Cost 89.37 Total added cost of this Change Order Contract amount prior to this Change Order Revised Contract Amount $1,911.06 $7,893.20 $ 9,804.26 Carpet Mill City of Moscow, Idaho C:\WPDOCS\P&R\CHANGE.ORD 94-31