Full Text
CITY OF MOSCO'..! CONTRACT CHANGE ORDER DATE: August 6, 1990 CHANGE ORDER NO. one ( 1) PROJECT NAME: Orchard Avenue Water] ine CONTRACTOR: Bodiford Construction PROJECT NO. 116-89 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE IN INCREASE IN CONTRACT PRICF CONTRACT PRICE 1. Furnish and install 140 ft. of a 3 inch dia. electrical conduit for the Ponderosa Booster Station 2. Excavation and repair of a private san. sewer drainfield within the route of the new water main along Orchard Ave. $456.11 757.00 - o - $1,213.11 TOTALS NET CHANGE IN CONTRACT PRICE JUSTIFICATION: see attached The sum of $1,231.11 the total contract price. is hereby added to (ADDED TO) (DEDUCTED FROM) The adjusted contract price to date is thereby $119,230.11 not changed (INCREASED) (DECREASED) tNOT CHAtiGED)by The time provided for completion is calendar days. This document will become a supplement to the contra_s;,t--and all provisions of the coptract wil 1 apply hereto. . Bodiford Construction.__ /