North Higgins Bike/Ped Project Schedule Managed by Public Works without Mayor authority resolution Advertise RFP for Design Services June 28 & July 5 Responses to RFP Due July 15 Select consultant July 16 Consultant agreement July 23 MDT Review July 31 Award Referral to Committee August 3 Public Works Committee August 5 City Council Approval August 10 Contract Executed August 17 Design Mid-August – Mid-October (8 weeks) MDT Review November – December Final Plans, specs and bid doc to MDT January 15 Deadline Managed by Public Works with Mayor authority resolution Advertise RFP for Design Services June 28 & July 5 Responses to RFP Due July 15 Select consultant July 16 Consultant agreement July 23 MDT Review July 31 Public Works Approval August 1 Design August – mid-October (10 weeks) MDT Review November – December Final Plans, specs and bid doc to MDT January 15 Deadline