North Higgins Bike/Ped Project Schedule Managed by Public Works without Mayor authority resolution  Advertise RFP for Design Services June 28 & July 5  Responses to RFP Due July 15  Select consultant July 16  Consultant agreement July 23  MDT Review July 31  Award Referral to Committee August 3  Public Works Committee August 5  City Council Approval August 10  Contract Executed August 17  Design Mid-August – Mid-October (8 weeks)  MDT Review November – December  Final Plans, specs and bid doc to MDT January 15 Deadline Managed by Public Works with Mayor authority resolution  Advertise RFP for Design Services June 28 & July 5  Responses to RFP Due July 15  Select consultant July 16  Consultant agreement July 23  MDT Review July 31  Public Works Approval August 1  Design August – mid-October (10 weeks)  MDT Review November – December  Final Plans, specs and bid doc to MDT January 15 Deadline