Full Text
Opinion of Probable Cost Exhibit E Project: Miller Creek Road Improvements - Project Cost Summary Project No.: 05-033 Prepared By: Monte Sipe Date: February 25, 2010 Description: Road Improvments for Miller Creek Road Briggs Street to Mockingbird Way Final Design Engineering Services (WGM Group) 287,401 $ City Administration - $ Engineering Total 287,401 $ Right-of-Way Right of Way Acquisition 329,490 $ Appraisal & Acquisition Services (DJA) 84,168 $ Right-of-way Total 413,658 $ Utility Relocation Utility Relocation Cost Share - $ Utility Engineering - $ Utility Total - $ Construction Road Construction Cost (LS Jensen Bid) 1,700,410 $ Construction Engineering Services (WGM Group) 165,873 $ Construction Total 1,866,283 $ Project Total 2,567,342 $ Total 2,567,342 $ Notes: Engineering Prepared by M. Sipe 2/25/2010 Page 1 Notes: Assumes that private utility relocation costs will be paid 100% by the utility companies. Includes land cost & cost to cure items Prepared by M. Sipe 2/25/2010 Page 1