Full Text
Project Name: Project Number: Comment No. Reviewer Comment Initial Dispositio n Response/Clarification Final Disposition Response By Date Verified By 1 Details B and E on sheet DT-01 show dimensions for the pickleball courts. Could you please provide clarification on the dimensions of the post tensions concrete slab and the dimensions of the concrete mow curb for the fence? A More detail provided A JBA 10/12/2023 SQ 2 Is there a spec section for the components of the pickleball courts, i.e. post tension concrete, chain link fence, surface, equipment? A Specs added A JBA 10/12/2023 SQ 3 Would 2” chain link fabric be accepted in lieu of 1 ¾” on the pickleball court? 2” fabric is a more cost effective and common size for pickleball courts A Changed to 2" Fabric A JBA 10/12/2023 SQ 4 Have calcs been done to design fence for wind/sound barrier material or is it assumed the supplier will provide these as part of the shop drawings submitted? B Supplier to provide B JBA 10/12/2023 SQ 5 Battery of 8 courts are undersized with 5’ between sideline and fence, would an alternate to provide full size courts with 7’ between sideline and fence be accepted? B The 8 courts are sized at 5 ft and the champion court is sized at 7 ft to be the tournament court B JBA 10/12/2023 SQ 6 Sheet GM-01 shows the note End wall begin curb at the northeast corner and PI Wall at northwest and south west corners of the pickleball courts. Is some portion of the courts on top of a wall and if so is there a detail for this? A Wall removed A JBA 10/12/2023 SQ 7 Sheet GD-01 shows a slope over the recommended 1% maximum slope on the pickleball courts. A Regraded to 1% Max slope A JBA 10/12/2023 SQ 8 Detail A, note 10 on sheet DT-02 calls for on all fence. Is there to be on only the 10’ fence, or 6’ and 4’ as well? Is the cost of the material to be included in the line for the chain link fence on the bid schedule? B Notes 1-12 apply to all fencing around the pickleball courts. B JBA 10/12/2023 SQ 9 Line 37 in the bid schedule identifies 123 linear feet of 10’ sound reduction screening, plans call out 265 linear feet of fencing with sound reduction screening. A Quantity updated to 265 feet in bid schedule and cost estimate A JBA 10/12/2023 SQ 11 Is there a soils report for the site? Are there any details on the PT court tendons/reinforcement that we can access to also. B No geotechnical report. Tendons and such are detailed in new special provision B JBA 10/12/2023 SQ 12 Do you have more details on what signs you will need for Item 26? B Item removed B JBA 10/12/2023 SQ 13 It has been such a long time since we talk original concept that I didn’t even realize there was lighting in the plans. I think we wanted to place risers, and potentially conduit, but not the lights. Maybe we don’t worry about it and go solar if we want lights in the future. B Item removed due to contract scope B JBA 10/12/2023 SQ 14 15 16 17 18 19 20 UT 21-050 B - Clarify/Discuss D - Dismiss Comment Comment Resolution Form Plans Disposition Codes Canyon Rim Park A - Accept Comment C - Disagree