Document Lewiston_doc_3bfb856640

Full Text

May 2, 2014 Jepson Brook Sewer Separation Phase VI Bid No. 2014-023 Bid Date: 5/8/14 ADDENDUM NO 2 Please make the following changes to the Specifications: Questions: 1. Will snouts/CB hoods still be required now that the CB sump has been changed to 2ft.? If they are still required are they required on all pipe diameters?  Catch Basin Hoods will still be required on all outlet pipes 15” or smaller. The two approved catch basin hoods are: Snout manufactured by Best Management Products PPF Catch Basin Hood manufactured by Plastic Pipe Fabrication END Department of Public Works • 103 Adams Ave • Lewiston, ME • 04240 • Voice Tel. [PHONE REDACTED] • Fax [PHONE REDACTED] • TTY/TDD [PHONE REDACTED] – www.lewistonmaine.gov Department of Public Works David A. Jones, P.E. Director