Full Text
Engineering Department 1559 Albion Ave, Burley Idaho 83318 Page 1 April 16, 2021 Concrete LID Addendum 2 Specifications: Remove and replace the bid schedule in the project plans and Addendum 1 with the bid tab pdf. Several of the LID applicants have changed the amount of work that is desired. Make sure to use the provided PDF or print out the provided E-Bid Tab Add 2 spreadsheet for the bid documents. Make sure to acknowledge both addenda in the bid. Drawings: Remove and replace plan sets in the Addendum 2 PDF starting with 8 and 24. Spreadsheet An Excel spreadsheet (E-Bid Tab Add 2) is provided that has each of the LID applicants. The spreadsheet is functional. The bidder must check his total with the total at the bottom of the bid to make sure no issues have happened to the spreadsheet. David R. Waldron, P.E. City Engineer David R. Waldron