August 11, 2022 Seefried and Hepworth Lane Project Addendum #3 Item #1 – On the Bid Sheet under Seefried and Hepworth Ln Roadway the 2 1/2” Hot Asphalt should be The Chip Seal and Fog Coat is to be done within 12 months of paving. There is an updated Bid Sheet on the city website. Item #2 – Chip sealing will be the entire roadway as the contractor will be paving the entire roadway width. Item #3 – If you want the CAD Files before Bidding, contact Steve Heath at Connect Engineering [PHONE REDACTED]. They said that they would supply them I just don’t know if that only meant to the successful bidder or anyone. Item #4 – Centerline is in the drawings and in the CAD File for most of the project, there is about 250 feet on Hepworth Lane down by Pendlebury Lane that has not been surveyed. The contractor is responsible for hiring a surveyor to do the surveying for the entire project. Item #5 – There is no Bid Bond just a payment & performance bond. End of Addendum #3