Special 1% Sales Tax CONSTRUCTION Project Status Report January 2009 PROJECT NAME: Belair Hills Subdivision Improvements CPB#: 324-04-203824335 TERMINI: Powell Rd & Gordon Intersection INSPECTOR: Alsbrook CONTRACTOR: Blair Construction PROJ TYPE: Drainage LENGTH: N/A CONCEPT: Roadway improvements, curb; gutter and sidewalk CONTRACT AMT: $6,446,337.64 NOTICE TO PRO: 7/1/2008 COMPLETE(%): ANTIC COMP 3/31/2010 PROJECT NAME: Bobby Jones Expy.@ S.R. 56 Add'l Loop CPB#: 322-04-292822156 TERMINI: I-520 @ S.R. 56 (Mike Padgett Hwy.) Intersection INSPECTOR: GDOT CONTRACTOR: Reeves Construction PROJ TYPE: Roadway LENGTH: 1.69 CONCEPT: Add West bound loop and lane to Apple Valley CONTRACT AMT: NOTICE TO PRO: COMPLETE(%): 100% ANTIC COMP 7/31/2007 PROJECT NAME: Bungalow Rd. CPB#: 323-04-299823595 TERMINI: Richmond Hill Rd. to U.S. 25 INSPECTOR: Michael Alsbrooks CONTRACTOR: Beams Pavement PROJ TYPE: Drainage LENGTH: 0.7 miles CONCEPT: Widening, curb, gutter, sidewalk, storm drain piping CONTRACT AMT: $3,519,984.30 NOTICE TO PRO: 7/27/2007 COMPLETE(%): 95% ANTIC COMP 1/15/2009 PROJECT NAME: Butt Memorial Bridge Repair CPB#: 323-04-200823130 TERMINI: 15th Street @ Augusta Canal INSPECTOR: Ladson CONTRACTOR: Engineered Restorations, Inc. PROJ TYPE: Drainage LENGTH: N/A CONCEPT: Emergency repair of concrete sub structure CONTRACT AMT: $0.00 NOTICE TO PRO: COMPLETE(%): 100% ANTIC COMP 5/11/2000 PROJECT NAME: East Boundary St. & Drainage CPB#: 324-04-201824117 TERMINI: Laney Walker Blvd. to Broad St. INSPECTOR: Ficklin CONTRACTOR: Mabus Brothers PROJ TYPE: Drainage LENGTH: CONCEPT: Roadway incl resurfaing, curb, gutter & sidewalk CONTRACT AMT: $4,289,091.23 NOTICE TO PRO: 11/30/2006 COMPLETE(%): 99% ANTIC COMP 9/11/2008 ---PAGE BREAK--- Special 1% Sales Tax CONSTRUCTION Project Status Report January 2009 PROJECT NAME: Fury's Ferry Rd. (S.R.28) CPB#: 322-04-292822205 TERMINI: Riverwatch Parkway to Columbia County Line INSPECTOR: GADOT CONTRACTOR: Reeves Construction Co. PROJ TYPE: Roadway LENGTH: 200 ft. CONCEPT: 4 lanes with 20 ft. raised median CONTRACT AMT: NOTICE TO PRO: COMPLETE(%): 100% ANTIC COMP 9/30/2006 PROJECT NAME: I-20 / I-520 Interchange & I - 20 Widening CPB#: 323-04-296823308 TERMINI: I-20 / I-520 Connector & I - 20 FM Belair Rd. to E of INSPECTOR: GDOT CONTRACTOR: Scott Bridge Co. & United Contractors PROJ TYPE: Roadway LENGTH: 6.25 CONCEPT: Interchange Reconstruction, Widening & Reconstruction CONTRACT AMT: NOTICE TO PRO: 6/4/2007 COMPLETE(%): 45% ANTIC COMP 10/31/2009 PROJECT NAME: I-20 Widening & Reconstruction CPB#: N/A TERMINI: From Warren Rd. Overpass to Augusta Canal INSPECTOR: GADOT CONTRACTOR: The Lane Construction Co. PROJ TYPE: Widening LENGTH: 3.070 CONCEPT: Widen to 3 lanes in each direction CONTRACT AMT: $0.00 NOTICE TO PRO: COMPLETE(%): 57% ANTIC COMP 10/31/2009 PROJECT NAME: Lover's Lane Evacuation Route CPB#: 323-04-207823001 TERMINI: INSPECTOR: Ficklin CONTRACTOR: Mabus Brothers PROJ TYPE: Roadway LENGTH: CONCEPT: CONTRACT AMT: $348,950.00 NOTICE TO PRO: COMPLETE(%): ANTIC COMP PROJECT NAME: Morgan Road Improvements CPB#: 323-04-296823665 TERMINI: Tobacco Rd. to U.S. 1 INSPECTOR: CONTRACTOR: PROJ TYPE: Roadway LENGTH: 1.35 CONCEPT: Widen roadway, install curb & gutters, sidewalks CONTRACT AMT: $4,426,497.96 NOTICE TO PRO: COMPLETE(%): ANTIC COMP ---PAGE BREAK--- Special 1% Sales Tax CONSTRUCTION Project Status Report January 2009 PROJECT NAME: Paving Various Roads, Ph. IX CPB#: 324-04-208824001 TERMINI: Varies INSPECTOR: CONTRACTOR: PROJ TYPE: Roadway LENGTH: N/A CONCEPT: Paving of selected dirt roads CONTRACT AMT: NOTICE TO PRO: COMPLETE(%): ANTIC COMP PROJECT NAME: Paving Various Roads, Ph. VIII CPB#: 323-04-200823808 TERMINI: Varies INSPECTOR: Williams CONTRACTOR: PROJ TYPE: Roadway LENGTH: N/A CONCEPT: Paving of selected dirt roads CONTRACT AMT: NOTICE TO PRO: COMPLETE(%): ANTIC COMP PROJECT NAME: Pinnacle Place Subdivision Erosion & CPB#: 322-04-203822642 TERMINI: INSPECTOR: Buddy Scott CONTRACTOR: Blair Construction PROJ TYPE: Drainage LENGTH: CONCEPT: Correct erosion in ditches. CONTRACT AMT: $641,111.12 NOTICE TO PRO: COMPLETE(%): 100 ANTIC COMP 11/30/2008 PROJECT NAME: Pointe West Subdivision Drainage CPB#: 323-04-203823372 TERMINI: Point West Dr. INSPECTOR: Martin CONTRACTOR: Blair Construction PROJ TYPE: Drainage LENGTH: CONCEPT: Perform Emergency Repair to failed corrugated metal CONTRACT AMT: $748,479.03 NOTICE TO PRO: 9/4/2008 COMPLETE(%): 70 ANTIC COMP 3/3/2009 PROJECT NAME: Rae's Creek Trunk Sewer Replacement, Ph IV CPB#: 327-04-208812301 TERMINI: (Camila Dr. Reconstruction) INSPECTOR: CONTRACTOR: PROJ TYPE: Drainage LENGTH: CONCEPT: CONTRACT AMT: NOTICE TO PRO: COMPLETE(%): ANTIC COMP ---PAGE BREAK--- Special 1% Sales Tax CONSTRUCTION Project Status Report January 2009 PROJECT NAME: Raes Creek, Sec. III CPB#: 326-04-288811357 TERMINI: Lake Olmstead to Berckman's Rd. INSPECTOR: Williams CONTRACTOR: Blair Construction PROJ TYPE: Drainage LENGTH: N/A CONCEPT: General creek improvements CONTRACT AMT: $907,734.80 NOTICE TO PRO: 6/7/2004 COMPLETE(%): 100% ANTIC COMP 12/10/2004 PROJECT NAME: Renovation of Training Center (Fire Dept.) CPB#: 324-03-207324003 TERMINI: Glenn Hills Drive/Bobby Jones off US 1 INSPECTOR: Michael Alsbrooks CONTRACTOR: Payne PROJ TYPE: LENGTH: CONCEPT: Drainage CONTRACT AMT: $387,670.80 NOTICE TO PRO: COMPLETE(%): 100% ANTIC COMP PROJECT NAME: Resurfacing Various Roads, Phase VIII CPB#: 324-04-203824045 TERMINI: Various locations INSPECTOR: Scott CONTRACTOR: Beams Contracting, Inc. PROJ TYPE:Resurfacing LENGTH: 13.137 CONCEPT: CONTRACT AMT: $1,147,654.18 NOTICE TO PRO: 10/27/2003 COMPLETE(%): 100% ANTIC COMP 10/22/2004 PROJECT NAME: S.R 4/15 @ CR2207 (Central Ave.) CPB#: 323-04-203823122 TERMINI: Intersection improvements INSPECTOR: GDOT CONTRACTOR: Beams Contracting PROJ TYPE: Traffic LENGTH: 0.10 CONCEPT: Signal, turn lanes, signing & marking CONTRACT AMT: NOTICE TO PRO: 11/5/2007 COMPLETE(%): ANTIC COMP 9/30/2008 PROJECT NAME: S.R. 121/US. 25 (Peach Orchard Rd.) CPB#: 322-04-204822882 TERMINI: Richmond County Line to S.R. 88 INSPECTOR: GDOT CONTRACTOR: Shepherd Const. Co, Inc. PROJ TYPE: Roadway LENGTH: 10 miles CONCEPT: 4 lanes with 44ft grass median CONTRACT AMT: NOTICE TO PRO: COMPLETE(%): 100% ANTIC COMP 7/31/2007 ---PAGE BREAK--- Special 1% Sales Tax CONSTRUCTION Project Status Report January 2009 PROJECT NAME: St. Sebastian Way/ Greene St/15 th St. CPB#: 324-04-202824003 TERMINI: Walton Way - Green; Greene - Broad; Broad - Reynolds INSPECTOR: GDOT CONTRACTOR: Sunbelt Structures, Inc. PROJ TYPE: New LENGTH: 2.55 CONCEPT: 4 Lanes /20' median + bridge over Canal CONTRACT AMT: NOTICE TO PRO: 5/15/2008 COMPLETE(%): 23% ANTIC COMP 12/31/2010 PROJECT NAME: Storm Pipe Replacement Good News Church CPB#: 322-04-206822001 TERMINI: INSPECTOR: Martin CONTRACTOR: CBH Construction PROJ TYPE: Drainage LENGTH: CONCEPT: CONTRACT AMT: $71,079.00 NOTICE TO PRO: 6/2/2008 COMPLETE(%): 99 ANTIC COMP 2/1/2009 PROJECT NAME: Washington Rd. Intersection CPB#: 324-04-201824371 TERMINI: Boy Scout to Center West Parkway INSPECTOR: Williams CONTRACTOR: Reeves Construction PROJ TYPE: Traffic LENGTH: CONCEPT: Intersection improvements CONTRACT AMT: $721,461.40 NOTICE TO PRO: COMPLETE(%): ANTIC COMP PROJECT NAME: Winchester Subdivision Drainage CPB#: 322-04-206822651 TERMINI: INSPECTOR: Michael Alsbrooks CONTRACTOR: Blair Construction PROJ TYPE: Drainage LENGTH: CONCEPT: Storm drain improvements CONTRACT AMT: $241,225.45 NOTICE TO PRO: 8/2/2007 COMPLETE(%): 100% ANTIC COMP 1/2/2008 PROJECT NAME: Windsor Spring Rd. CPB#: 323-04-296823516 TERMINI: US 25 to Wyman St. to Old Louisville Rd. INSPECTOR: Williams CONTRACTOR: Mabus Brothers Construction, Co. PROJ TYPE: Roadway LENGTH: 0.88 CONCEPT: Roadway curb & gutter, sidewalks, bridge CONTRACT AMT: $4,549,000.00 NOTICE TO PRO: 9/2/2008 COMPLETE(%): 10 ANTIC COMP 3/30/2009